Articles tagged with: Mining

The Anatomy of 43-101 Chapter 16 – Mining (Part 2)

Part 2 of this blog post will focus on the remaining engineering work to finish Chapter 16 of the Technical Report. We only wrote about half of it in Part 1. The mining engineer can generally handle the rest of these tasks without requiring a lot of external input. You can read Part 1 at this link “The Anatomy of 43-101 Chapter 16 – Mining (Part 1)”.
The pit design and phases were completed at the end of Part 1, and we can move on to scheduling.

4. Production Scheduling

Once the pit design is complete, everyone will be calling for the production schedule as soon as possible. Others on the team are waiting for it. The tailings engineers need the production schedule for the tailings stage design. The process engineers need the scheduled head grades to finalize sizing the plant components. The client wants the schedule to plug into their internal cashflow model for a quick peek at the economics.
However, before the mine engineer can start scheduling, the dilution approach needs to be selected. Dilution is waste that is mixed in with ore during mining. A high amount of dilution can dramatically lower the processed head grades. There may be a desire to “low ball” the dilution to make the grades look better, but the engineer should base the dilution on what they would expect to see.
Two dilution approaches are common. One can either construct a diluted block model; or one can apply dilution afterwards in the production schedule. I have used both approaches at different times.
The production schedule must be on a diluted basis, since that represents what the processing plant will actually see.
Generally, two different production schedules must be created: (i) a Mining schedule, and (ii) a Processing schedule. In some instances, they may be one and the same schedule. However, if any ore stockpiling is done, then the Mining schedule will be separate from the Processing schedule.
The Mining schedule shows ore going directly to the plant and ore going into the stockpiles. The Processing schedule will show ore delivered directly from the mine and ore reclaimed from stockpiles. Building stockpiles and pulling ore from stockpiles are two independent activities.
ore stockpileSometimes lower grade stockpiles are built up by the mine each year but only processed at the end of the mine life. Periodically the ore mining rate may exceed the processing rate and other times it may be less.  This is where the stockpile provides its service, smoothing the ore delivery to the plant.
Scheduling can be done with variable time periods. Perhaps the schedule is generated using monthly time periods, or quarters, or years.
The 43-101 report will normally show the annual production schedule, but that does not mean it was generated that way. I prefer to use short time periods (monthly or quarterly) for the entire mine life, to ensure ore is always available to feed the plant. A 10 year mine life would result in 120 monthly time periods, so output spreadsheets can get large.
Scheduling can be done manually (in Excel) or by using commercial software, like Datamine’s NPVS. The commercial software is better in that it allows one to run different scenarios more quickly, and it does a lot of the thinking for the engineer. It also does a good job of stockpile tracking. It also decides when it is necessary to transition to mining in satellite pits.
Once the schedules are finalized, they are normally reviewed by the client for approval. The strip ratio and ore grade profile by date are of interest. One may then be asked to look to at different stockpiling approaches to see if an NPV (i.e. head grade) improvement is possible.
One can stockpile lower grade ore and feed the plant with better grade by mining at a higher rate with more equipment. One might need to examine iterative schedules of that type.
Sometimes one must take two steps backwards and re-design some of the initial pit phases to reduce waste stripping or improve grades. Then one would run the schedules again until getting one that satisfies everyone.
Now that the schedule is complete, we can write up the Chapter 16 text up to page 15. We’re getting closer to the end.

5. Site Layout Design

Diavik mines

With the pit tonnages and mining sequence from the schedule, the mine engineers can start to look at the site layout (waste dumps and haul roads). Normally the tailings engineers will be responsible for the tailings layout. However, if there is no tailings engineer on the PEA team, the mining engineer may look after this too.
First there is a need for a waste balance. This defines how much mined overburden or waste rock will be needed to build haulroads, laydown pads, and tailings dams. Then the remaining waste volume must be placed into waste dumps.
Hopefully the tailings engineers have finished their tailings dam construction sequence by this time to provide their rockfill needs (although unlikely if you only gave them the production schedule two days ago).
The geotechnical engineers will provide the waste dump design criteria; for example, 3:1 overall side slope using 15m high dump lifts. Ideally it is nice to have soil and foundation information beneath the waste dump sites, but at PEA stage most often this isn’t available. The dump locations are only being defined now.
The mining engineers will size the various waste dumps to their required capacity. Then they can lay out the mine haulroads from the pit ramps exits to the ore crusher, the ore stockpiles, and to each waste dump.
That’s it for the site layout input. Add another 2 pages to Chapter 16. Now the mining engineers can look at the mining equipment fleet.

6. Fleet Sizing and Mining Manpower

The last task for the mine engineer in Chapter 16 is estimating the open pit equipment fleet and manpower needs. The capital and operating costs for the mining operation will also be calculated as part of this work, but the costs are only presented in Chapter 21.
The primary pieces of equipment are the haul trucks. They can range in size from 30 tonnes to 350 tonnes and anywhere in between.
Typically, the larger the equipment is, the lower the unit cost ($/t), especially in jurisdictions where labor costs are high. One doesn’t want a mine fleet with only 5 trucks nor one with 50 trucks. So where is the happy medium?
Once the schedule and site layout are complete, the mine engineers can run the truck haul cycles, in minutes. They need to estimate the time to drive from the pit face, up the ramp, to the waste dump, to the ore crusher, and return back into the mine. Cycle times determine the truck productivity, in tonnes per hour per truck and include the time to load the truck. Some destinations may have long cycle times (to a far off crusher) while others may be quick (to an adjacent waste dump).

Open Pit Slope

The cycle time must be calculated for each material type going to each destination. As the pit deepens, the cycle times increase.
Very simplistically, if a 100 tonne truck has a 20 minute cycle time, it can do three cycles in an hour (300 tph). If one has to mine 10 million tonnes of ore per year, then that would require 33,300 truck hours. If a single truck provides 6500 operating hours per year, that activity would require a fleet of 5 trucks. The same calculation goes for waste.
The total trucking hours will vary year to year as waste stripping tonnages change or haul cycle times increase in deeper pits. The required truck fleet may vary year to year.  Keeping haul distance short and haul cycles quick is the key to a lower cost mine.
The mine engineers undertake the productivity calculations for loading equipment to estimate annual operating hours, and the required shovel / loader fleet size.
The support equipment needs (dozers, graders, pickups, mechanics trucks, etc.) are typically fixed. For example, 2 graders per year regardless if the annual tonnages mined fluctuate.
The support equipment needs are normally based on the mining engineer’s experience. Hence the benefit of actually working at a mine at some point in your career.
Blasting includes both the blasthole drilling activity and hole charging. The mining engineer estimates drill productivity and specifications based on the bench height, the expected rock mass quality, and the power factor (kg/t) need to properly demolish the rock.
Finally, the mine operation manpower is estimated based on all the equipment operating hours as well as the fixed number of personnel to support and supervise the mine.
This essentially concludes the mining information presented in Chapter 16 of a typical 43-101 open pit report.

Conclusion

These two blog posts hopefully give an overview of some of the things that mining engineers do as part of their jobs. Hopefully the posts also shed light on the amount of work that goes into Chapter 16 of a 43-101 report. While that chapter may not seem that long compared to some of the others, a lot of the effort is behind the scenes.
Some will say PEA’s are not very accurate documents that should be taken with a grain of salt. One should understand that engineers are working with a limited amount of information at this early stage while forming the concept for the proposed operation.
The subsequent study stages are where more accurate costs are expected and can be demanded.
I don’t know if this overview makes one want to sign up to be a mining engineer or learn to code instead. None of this is rocket science; it just requires practical thinking.
If young people want to get into mining, but not sure into which aspect, I suggest go read through a 43-101 report. There are sections describing exploration, resource modelling, mine engineering, metallurgy, geotechnical engineering, environmental, and financial modelling. Its all in one document. See if any of these areas are of interest to you. Universities should use 43-101 reports as part of their mining engineering curriculum.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Top Ten Mining Podcasts

Podcasts. There are thousands of them out there, free for anyone to access. I regularly listen to them on all sorts of topics ranging from sports, politics, and even mining. This blog post is about my top mining podcasts that I find entertaining and/or educational. There are likely others missing from this playlist, but one only has so much time in a day.
On YouTube, there are also a lot of educational videos related to mining. Some of the same audio podcast episodes are also available on the YouTube platform. Given an option, I prefer the audio-only podcast format over YouTube.
One doesn’t need to sit there focusing on a video screen. With podcasts, you can do other things at the same time, like exercise, walk the dog, drive a car, etc. One has freedom to multi-task, something that the video format doesn’t allow.
When listening to podcasts, I used the Android phone app called Podcast Addict. However, most likely there are plenty of other smartphone apps to use.

Mining Podcast Categories

In my experience, mining podcasts typically fall into one of two categories; Mining Investment; and Technical Discussions.
Mining Investment: These are the investor targeted interviews, chatting with corporate executives or newsletter writers. They discuss what is new with their companies or what is happening in the industry. From an engineer’s perspective (not as an investor), I listen to a few of these to catch up on projects that I worked on in the past, or to learn how different executives strategize. These interviews are often paid for promotions by the company, so sometimes the interview questions can be the softball type. I’m not sure how often the interview questions are actually provided in advance.
Technical Discussions: There are also a few podcasts related to technical discussions on geology, exploration methods, resource modelling, mining software, and mining services. I have not found any podcasts specifically related to mine engineering or mineral processing. Most are geared towards the geological and exploration aspects of the industry.
Pick and choose. One can’t listen to all the podcast episodes available or else you wouldn’t have time to do anything else in life. You would also become bored since much of it can be repetitive.
Therefore, I follow multiple podcasters, get updates on their new episodes, and then pick and choose from there. I probably only listen to 10%-20% of the episodes, i.e. only those that are of real interest to me.
Sometimes, especially with investor presentations, the same executives will appear on multiple podcasts. You only need to hear the story once. As well, some executives will be returning frequently to the same podcast with not a lot new to say from their last interview. They need to catch the eyes of investors.
The podcast host will have a lot to do with the style of discussion. Some are better than others. Sometimes the interviewing style is dull and unexciting, even through the topic itself may be great. The following are some of the mining podcasters that I follow.

Mining Investment Podcasts

  • This list are my favorites, in order of preference. They are the only ones I follow
  • Mining Stock Education (680 episodes) https://www.miningstockeducation.com/ This podcast can have some lively discussion that focus on both the positives and negatives of mining investment. Some guests definitely provide great learnings on the inner workings of the industry.
  • Crux Investor (2500 episodes) https://www.cruxinvestor.com/ Matthew and Merlin have an engaging interview style, and sometimes will have a hard edge, putting interviewees on the spot. They say they “…exist to cut through the jargon, bias and bluster.”
  • Mining Stock Daily (2800 episodes) Mining Stock Daily, hosted by Trevor Hall, provides a daily 8 minute overview of overnight mining news and will also have long form discussions on finance, macro economics, and corporate exploration news.
  • Global Lithium Podcast (130 episodes) is hosted by Joe Lowry, known as “Mr Lithium” who is a 30 plus year industry veteran. For me, this podcast is the “go to” on everything lithium, whether brines or hard rock production.
  • Money of Mine (170 episodes) This Aussie mining podcast focusses mainly on Aussie companies, but the three hosts have an interesting style and not afraid to say what they think. Listening to their Aussie accents always makes me think of the Crocodile Dundee movies.

Technical / Informational Mining Podcasts

These are podcasts on the informational and technical side of mining. Unfortunately for we engineers, they mainly focus on geology.
  • Fresh Thinking by Optiro-Snowden (53 episodes) This podcast is hosted by Snowdon – Optiro consultants. They typically focus on resource modelling and grade reconciliation aspects. The episodes are fairly short (15 mins), which is nice. Although I am not a resource modeller, I can always learn more about the black art of resource modelling.
  • The Northern Mining Podcast (400 episodes) This podcast provides general industry news, as the Northern Miner newspaper does. It also has interviews with key industry players, but generally avoids the company investor relation interviews.
  • Discovery to Recovery (50 episodes) This is a podcast produced by the Society of Economic Geologists (SEG), brings geoscience and technology stories from the world of ore deposits. This podcast can be harder to listen to, getting heavy into geology discussions beyond my expertise.
  • Exploration Radio (73 episodes) This is a podcast focusing on the past, present and future of exploration. They don’t seem to post very often, but can have interesting topics, even for an engineer.
That is the end of my list.
To the best of my knowledge, there are a lack of podcasts related to mine engineering, for topics such as pit optimization, mine design, scheduling, equipment selection, and costing.
There is one podcast on mine scheduling by Mark Bowater, author of “Crimes Against Mine Planning”, but I cannot find it on any podcast platform.
Another honorable mention is Antonio at https://www.youtube.com/@ResourceTalks/ who does a great job at interviewing executives. The downside is that I don’t think he is on audio-podcast format and his episodes are over 1 hour, or 3600 seconds as he likes to present it. That’s beyond my normal attention span.
Update:  A follower of my blog posts has suggested a mining investing site on YouTube called “Junior Resource Investing“.    The host is Matthew Mick, seems to have a preference for Ni and base metal projects,  interviews are up to 50 minutes each with well prepared questions.  Check it out.  I can’t find it on a podcast platform as of yet.

Conclusion

There is no shortage of material in the podcast world about the mining industry. It all depends on what interests you the most. There is even more mining information available on YouTube, if you have the time to sit and watch videos. Nevertheless the audio-only platform is great, although you don’t get to see the charts being discussed. That’s fine with me, particularly if they take a few seconds to describe the chart.
Let us know what mining podcasts you enjoy and would recommend. I have room to add one more to my list of 9 mining podcasts. I don’t actually have 10 favorites yet.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Mine Builders vs Mine Vendors

Normally when Major or Intermediate miners advance their projects through the study stages, they usually have the intent to build the mine at some time.  Sometimes they may decide to sell the project if it no longer fits in their corporate vision or if they desperately need some cash.   However, selling the project was likely not their initial intent.
On the other hand, Junior miners tend to follow one of two paths.  They are either on (a) the Mine Builder path, or (b) the Mine Vendor path (i.e. sell the project).  In this article, I will present some examples of companies on each path.   There will also be some discussion on whether the engineers undertaking the early stage studies (e.g., PEA’s) should be considering the path being followed.

The Mine Builder Path

The Mine Builder generally follows a systematic approach, as sketched out in the image below.  The project advances from drilling to Mineral Resource Estimate (MRE), scoping study (PEA), then through the Pre-Feasibility Study (PFS) and/or Feasibility Study (FS) stages.  Environmental permitting is normally proceeding in conjunction with the engineering. Once the FS is complete, the next hurdles for the Mine Builder are financing and construction.   The path is fairly orderly.
Mining Project Builder Path
The amount of the exploration drilling is only needed to define an economic resource to the Measured and Indicated classifications.   There is no requirement to delineate the mineral resource on the entire property since there will be time to do that during production.   Demonstrating an economic resource, with some upside potential, is often sufficient for the Mine Builder.
Three examples of companies on the Builder path are shown below; Orla Camino Rojo gold project (in operation), SilverCrest Las Chispas gold project (in operation), and Nexgen Rook uranium project (financing stage).   Although the duration of each timeline is different due to different project complexities, the development paths are consistent.  Most junior miners would not consider themselves on the Builder path.

The Mine Vendor Path

Mine Vendor type organizations have the primary goal of selling their project.  These companies may consist of management teams that don’t have the desire, comfort, or capability to put a mine into production. For example, this is often the case with companies founded by exploration geologists, whereby their plan is to explore, grow, and sell all (or part) of the project.   In other cases the Junior miner realizes their project is large with a high capital cost.  That capital cost is beyond the financial capability of the company.  Hence a deep-pocket partner is required or an outright sale is preferred.
Mining Project Vendor Path
The Mine Vendors tend to follow a different development path than the Mine Builders. They don’t have the same long term objectives.  Vendors want out at some point.
The Vendor path can be more irregular, with multiple studies undertaken at different levels of detail, sometimes stepping back to lower level of studies as more information is acquired.  Their object is to make the project look good to potential buyers, and look better than their junior miner competitors also for sale.  Often this ongoing project improvement process is termed “de-risking”.
Not only must the Vendors demonstrate an economic resource, they must demonstrate a highly valuable resource to maximize the acquisition price for the shareholders.  They will try to do this through multiple drill campaigns followed by multiple studies, each one looking better than the prior one.
Sometimes you will see a management team indicate that, if the project isn’t sold, they are going to put it into production themselves.  This may be true in some cases, or simply part of the negotiating game to try to maximize the acquisition price.
Two quick examples of companies on the Vendor path are shown below: Western Copper Casino project and Seabridge KSM project.  The durations of these development timelines are extensive and expensive, while waiting for an interested buyer.   During these periods, the companies may continue to spend money de-risk the project further.  The hope is that the company can eventually make the project attractive or that changing market conditions will make it attractive for them.   Unfortunately, there is always the possibility that no buyer will ever come along.

Engineer’s Perspective

One question is whether the independent geologists and engineers working on the advanced studies should be aware of the path the company is following. Is the company a Builder or a Vendor?
Some may feel that the technical work should be independent of the path being followed.  Based on my experience as both an owner’s representative and independent study QP, I have a somewhat different opinion.  The technical work should be tailored to the intended path.

The Engineer on the Mine Builder Path: 

If an engineer understands that a Mine Builder’s project will move from PEA to PFS to FS in rapid succession, then there is more incentive to ensure each study is somewhat integrated.
For example, a PEA will use Inferred resources in the economics.  However, if the project will advance to the PFS stage, where Inferred cannot be used, then it is important for the PEA to understand the role that Inferred plays in the economics.    How much drilling will be needed to upgrade Inferred resource to Indicated for the PFS, if needed at all?
Typically, capital costs tend to increase as advancing studies get more accurate due to greater levels of engineering.   A Builder wants to avoid large cost increases when moving from PEA to PFS to FS.  Therefore, when costing at the PEA stage, one may wish to increase contingency or use conservative design assumptions.  After all, one is not trying to sell or promote the project internally, but rather move it towards production.
There is no value to the Mine Builder by fooling themselves with low-balled cost estimates.  (Although some may argue there is still a desire to low ball costs to get management to approve the project).    Conversely Mine Vendors do have some incentive to low ball the costs.
Perhaps some of the recent project capital cost over-runs we have seen is that the Vendor mentality was used at the PEA stage to optimistically set the capital cost baseline.  Subsequent studies were then forced to conform to that initial baseline. Ultimately construction will be the arbiter on the true project cost.  Hence there is no real value in underestimating costs, ultimately making management appear incompetent if costs do over-run.
The Mine Builder will also be advancing environmental permitting simultaneously with their advanced studies.  Hence at the early stage (PEA) it is important to properly define the site layout, processing method, production rate, facility locations, etc. since they all feed into the permitting documents.
Changing significant design details in the future will set back the permitting and construction timelines.  Hence, for the Mine Builder, the engineers should focus on getting the design criteria mostly correct at the PEA stage.  For the Mine Vendor, this is not as important since multiple studies are being planned for in the future anyway.

The Engineer on the Mine Vendor Path: 

The objective of the Mine Vendor is to make the project attractive to potential buyers.  There is less urgency in fast tracking detailed engineering and permitting.
It is not uncommon to see multiple drilling programs, followed my multiple studies of scenarios with different size, production rate, and layout.   The degree of engineering conservativeness in design and costing is less critical since future studies may be on substantially different sized projects.
The role that the Inferred resource plays in the economics is also less important at this time, since a lot more drilling may be coming. The Vendor’s objective tends to be on maximizing resource size not necessarily optimizing resource classification.
While the Mine Vendor may also be advancing environmental permitting as another way to de-risk the project, the project design may still be in flux as the resource size changes.  Major modifications to the plan may cause permitting to stop and re-start, leading to an extended project timeline and wasted money.
There is also risk in starting the permitting with a project definition that isn’t of economic interest to future buyers.  Sometimes the Vendor may be making regulatory commitments that constrain the operating flexibility of future mine operators. Its easy to commit to things when you aren’t the one having to live up to them.
The Mine Vendor will also de-risk the project by moving from PEA to PFS and even to FS.   The caution with completing a FS is that it is a costly study and essentially brings one to the end of the study line.  What does the company do next if there is still no buyer?
Feasibility studies also have a shelf life, with the cost estimates and economics becoming inaccurate after a few years.  Some companies may re-examine the project, re-frame it, and jump back to the PEA or PFS stages.  There can be an on-going study loop, requiring continued funding with no guarantee of a sale in sight.  Often feasibility studies have the dual role of trying to boost the share price and market cap, as well as frame the project for potential buyers.

Conclusion

As an engineer, it is helpful to understand the objectives of the project owner and then tailor the technical studies to meet those objectives.  This does not mean low balling costs to make the study a promotional tool.  It means focusing on what is important.  It means recognizing the path, and what doesn’t need to be engineered in detail at this time.  This may save the client time, money, and improve credibility in the long run.
In many cases, the precise size of the deposit is less important than understanding the site, access, water supply, local community issues, the environmentally acceptable location for dumps and tailings, etc..   It can be more important to focus on these issues rather than having a detailed mine plan with multiple pit phases that immediately becomes obsolete in a few months after the next drilling campaign.
Potential buyers will have their own technical team that will develop their own opinions on what the project should be and what it should cost.   Just because a Mine Vendor has a feasibility study in hand, doesn’t mean a potential buyer will believe it.
This post is just a brief discussion of mining project timelines.   For those interested, there a few additional project timelines for curiosity purposes.   Each path is unique because no two mining projects are the same.  You can find these examples at this link “Mining Project Timelines”.
Let me know about other interesting projects that have interesting paths to learn from.  I can add them to the list.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/

 

Share

Don’t Cut Corners, Cut Cross-Sections Instead

Exploration cross-sectionThis article is about the benefit of preparing (cutting) more geological cross-sections and the value they bring.
Geological sections are one of the easiest ways to explain the character of an orebody. They have an inherent simplicity yet provide more information than any other mining related graphic.
Some sections can be simple cartoon-like images while others can be technically complicated, presenting detailed geological data.
Cartoon-stylized sections are typically used to describe the general nature of the orebody. The detailed sections can present technical data such as drill hole traces, color coded assays intervals, ore block grades, ore zone interpretations, mineral classifications, etc.
Sections provide a level of clarity to everyone, including to those new to the mining industry as well as those with decades of experience.
This article briefly describes what story I (as an engineer) am looking for in sections. Geologists may have a different view on what they conclude when reviewing geological sections.
I will describe the three types of geological sections that one can cut and what each may be describing. The three types are: (1) longitudinal (long) sections; (2) cross-sections; (3) bench (level) plans. Each plays a different role in helping to understand the orebody and mining environment.
There is also another way to share simple geological images via3D PDF files. I will provide an example later.

Longitudinal (Long) Sections

Geological long section examplesLong sections are aligned along the long axis of the deposit. They can be vertically oriented, although sometimes they may be tilted to follow the dip angle of an ore zone.
Long sections are typically shown for narrow structure style deposits (e.g. gold veins) and are typically less relevant for bulk deposits (e.g. porphyry).
The information garnered from long sections includes:
  • The lateral extent of the mineralized structure, which can be in hundred of metres or even kilometers. This provides a sense for how large the entire system is. Sometimes these sections may show geophysics, drilling to defend the basis for the regional interpretation.
  • Long sections will often highlight the drill hole pierce points to illustrate how well the mineralized zone is drilled off. Is the ore zone defined with a good drill density or are there only widely spaced holes? As well, long sections can show how deep ore zone has been defined by drilling. On some projects, a few widely spaced deep holes, although insufficient for resource estimation purposes, may confirm that the ore zone extends to great depth. This bodes well for potential development in that a long life deposit may exist.
  • Sometimes the long section drill intercept pierce points can be contoured on grade, thickness, or grade-thickness. This information provides a sense for the uniformity (or variability) of the ore zone. It also shows the elevations of the higher grade zones, if the deposit is more likely an open pit mine, an underground mine, or a combination of both.

Cross-Sections

Geological pit sectionCross-sections are generally the most popular geological sections seen in presentations. These are vertical slices aligned perpendicular to the strike of the orebody. They can show the ore zone interpretation, drill holes traces, assays, rock types, and/or color-coded resource block grades.
As an engineer, my greatest interest is in seeing the resource blocks, color coded by grade. Sometimes open pit shells may be included on the section to define the potential mining volume. The engineering information garnered from block model cross-sections includes:
  • Where are the higher-grade areas located; at depth or near surface?
  • If a pit shell profile is included, what will the relative strip ratio look like? Are the ore zones relatively narrow compared to the size of the pit?
  • How will the topography impact on the pit shape? In mountainous terrain, will a push-back on pit wall result in the need to climb up a hillside and create a very high pit slope? This can result in high stripping ratios or difficult mining conditions.
  • Does the ore zone extend deeper and if one wants to push the pit a bit deeper, is there a high incremental strip ratio to do this? Does one need to strip a lot of waste to gain a bit more ore?
  • Are the widths of the mineable ore zones narrow or wide, or are there multiple ore zones separated by internal waste zones? This may indicate if lower-cost bulk mining is possible, or if higher cost selective mining is required to minimize waste dilution.
  • How difficult will it be to maintain grade control? For example, narrow veins being mined using a 10 metre bench height and 7 metre blast pattern will have difficulty in defining the ore /waste contacts.
  • Cross-sections that show the ore blocks color coded by classification (Measured, Indicated, Inferred), illustrate where the less reliable (Inferred) resources are located and how much relative tonnage may be in the more certain Measured and Indicated categories.
Geological cross-section exampleWhen looking at cross-sections, it is always important to look at multiple cross-sections across the orebody. Too often in reports one may be presented with the widest and juiciest ore zone, as if that was typical for the entire orebody.  It likely is not typical.
Stepping away from that one section to look at others is important. Possibly the character of the ore zones changes and hence its important to cut multiple sections along the orebody.

Bench (Level) Plans

Mining Bench PlansBench plans (or level plans) are horizontal slices across the ore body at various elevations. In these sections one is looking down on the orebody from above.
Level plans are typically less common to see in presentations, although they are very useful. The level plans may show geological detail, rock types, ore zone interpretations, ore block grades, and underground workings.
The bench plan represents what the open pit mining crews would see as they are working along a bench in the pit. The information garnered from bench plans that include the block model grades includes:
  • Where are the higher-grade areas found on a level? Are these higher grade areas continuous or do they consist of higher grade pockets scattered amongst lower grade blocks?
  • Do the ore zones swell or pinch out on a bench? A vertical cross-section may give a false sense the ore zones are uniform. The bench plan gives an indication on how complicated mining, grade control, and dilution control might be for operators.
  • Do the ore zones on a bench level extend out beyond the pit walls and is there potential to expand the pit to capture that ore?
  • On a given bench what will the strip ratio be? Are the ore zones small compared to the total area of the bench?
As recommended with cross-sections, when looking at bench plans, one should try to look at multiple elevations.  The mineability of the ore zones may change as one moves vertically upwards or downwards through a deposit.

Never mind cross-sections – give me 3D

While geological sections are great, another way to present the orebody is with 3D PDF files to allow users to view the deposit in three-dimensions. Web platforms like VRIFY are great, but I have been told they sometimes can be slow to use.
Mining 3D PDF file3D PDF files can be created by some of the geological software packages. They can export specific data of interest; for example topography, ore zone wireframes, underground workings, and block model information. These 3D files allows anyone to rotate an image, zoom in as needed and turn layers off and on.
You can also create your own simplistic cross-sections through the pdf menus (see image).
A simple example of such a 3D PDF file can be downloaded at this link (3D DPF File Example). It only includes two pit designs and some ore blocks to keep it simple.
The nice thing about these PDF files is that one doesn’t need a standalone viewer program (e.g. Leapfrog viewer) to view them. They are also not huge in size. As far as I know 3D PDF files only work with Adobe Reader, which most everyone already has.  It would be good if companies made such 3D PDF files downloadable along with their corporate PowerPoint presentations.

Conclusion

Exploration cross-section exampleThe different types of geological sections all provide useful information. Don’t focus only on cross-sections, and don’t focus only on one typical section.  Create more sections at different orientations to help everyone understand better.
In 2019 I wrote an article describing the lack of geological cross-sections in many 43-101 technical reports. The link to that article is her “43-101 Reports – What Sections Are Missing?
Geological sections are some of the first items I look for in a report. Sometimes they can be hidden away in the appendices at the back of the report. If they are available, take the time to actually study them since they can explain more than you realize.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Polymetallic Drill Results – Interesting or Not?

A while ago I posted an article about how one can evaluate the economic potential of a gold deposit using early-stage exploration intercepts.  That article can be found at this link.   Doing the same evaluation for a polymetallic deposit is a bit more challenging.  There will be different metals of interest, with variable grades, prices, and process recoveries.
When disclosing polymetallic drill results, many companies will convert the multiple metal grades into a single equivalent grade.  I am not a big proponent of that approach.
I prefer using the rock value, whether calculated as a recoverable “NSR dollar value per tonne” or as an “insitu value per tonne”.  Either rock value is fine for my purposes.
Interestingly NI 43-101 prohibits the disclosure of insitu rock value but allows the use of metal-equivalents.  In my view this is a bit counter-intuitive since the equivalent grade  can be more misleading than rock value.

What can drill intercepts show

The three aspects that interest me the most when looking at early-stage drill results are:
  1. The economic value of the rock (in $/t tonne). This can either be “insitu value” (assuming 100% recovery, 100% payable) or the “NSR value” incorporating recovery and payable factors (if available).   Personally, the 100% insitu value is simpler to calculate and assess.
  2. The depth to the top of the economic zone, which indicates if this deposit would be a lower cost open pit mine or must be a higher cost underground mine.
  3. The length of the economic intervals, which indicates whether bulk mining approaches are viable versus the need to selectively mine narrow ore zones. The economic interval lengths also give a sense for the potential tonnage size (i.e. is it a big deposit or a small one).
There are two types of early-stage exploration data that can be examined with respect to the three items of interest described above.  They are (i) the drill hole assay data and (ii) the drill hole "intercepts of interest".  I will show an example of each in this post using sample data from an actual exploration program.
One can examine individual drill hole assays to calculate the rock value profile along each drill hole.  One can also examine the rock values for the major and minor intervals of interest reported in company news releases.
I normally like to examine both, but the intervals of interest data is publicly disclosed and more readily available.  Drill hole assays are often a bit harder, if not impossible, to track down.

Economic Parameters

In a polymetallic deposit, the insitu rock value is simply the summation of value of the individual metal, based on their respective assay grades.   An NSR rock value would apply an adjustment for metal recoveries and smelter payables, thereby lowering the insitu rock value somewhat.  However the insitu value is fine if there is no metallurgical or process data to rely upon.
Next one must determine what insitu rock value is deemed potentially economic, i.e. the breakeven cutoff.
One can estimate a processing cost and G&A cost.  In an open pit scenario, one doesn’t include the mining cost since the goal is to decide whether to send a truck to the waste dump or to the crusher. Only the processing and G&A cost musts be recovered by the ore value.   In an underground mining scenario, one would include the mining cost in the cutoff calculation.
In our example, lets assume a unit processing cost of $12/t and a G&A cost of $$2/t, for a combined cost of $14/t.    If we envision a metal recovery range of 75%-95%, we can assume 85% for now.
If we envision a smelter payable range of 75% to 95%, we will assume 85% for that also.
The “NSR factor” would now be 85% x 85% or 75%. Therefore, if the breakeven cost is $14/t, then one should target to mine rock with an insitu value greater than $20/tonne  (i.e. $14 / 0.75). This would be the approximate ore vs waste cutoff.  It is still only ballpark estimate at this  early stage, but good enough for this type of review.
Normally it would be nice to see the average head grade (or rock value) at 3 to 4 times greater than the cutoff grade.  This is not a necessity but it is a positive factor.
For example, in a gold deposit with a 0.3 g/t cutoff, one would like to see average head grades at least 0.9 to 1.2 g/t or more.  If the average head grade is close to the cutoff grade, then possibly the orebody tonnage may be very sensitive to changes in cutoff.  This may not be a good thing.
In our example, with a breakeven cutoff rock value of $20/t, one would like to see some ore zones with insitu values 3-4x higher, or above $60 - $80/t.   We can target >$70/t rock as a "nice to have" with $20/t as the cutoff.
So far, its all pretty simple. Let’s look at some actual exploration data to see how to apply this approach.
Our example will be a polymetallic deposit containing four metals of interest; copper, gold, cobalt, and iron.  One can examine  a few drill holes as well as the intervals of interest.
Metal prices used in this example are Cu = $4/lb, Au = $1980/oz, Co = $15.50/lb, Fe concentrate = $100/tonne, assuming 100% recovery and 100% payable for everything.

Drill Hole Assays Examples

The following three graphs show down hole profiles for Drill Holes A, B, C.  For each hole there are two plots. One plot shows the insitu rock values down the hole.  The second plot is the same, except the x-axis minimum has been set to the breakeven cutoff value of $20/t. This is done simply to highlight the potentially economic zones.
Hole A:
Shows positive economic results with ore quality rock starting near surface and extending down to 120 metres.
While many of the assay values are between $20-$70/t there are a significant number exceeding $70/t.
This hole has good economic potential for production.
Polymetallic drill hole evaluation
Hole B:
Shows positive economic results with economic rock starting near surface.  There are multiple economic zones extending all the way down to 370 metres.
The upper part of the hole, from 40m to 100m, shows multiple assay values exceeding the $70 target.
A second potentially economic zone is seen at a depth of 130m to 190m, which is still within the open pit mining range.
This hole also has good economic potential.
Polymetallic drill hole evaluation
Hole C:
For comparison purposes, Hole C is neutral in that while there are multiple potentially economic zones, they have lower insitu value.
This hole doesn't have the economic consistency that was seen in Holes A and B.
Possibly this hole may be near the edge of the ore body, in which case such a profile is not unexpected.
Polymetallic drill hole evaluation
Normally I would not spend a lot of time examining holes with little to no grade.  Some may consider this as a biased view.   However, every orebody has its limits, and what is occurring along the edges isn’t that critical in my view.
My objective is to understand what is happening in the core of the orebody, since that is what will dictate the overall economics.  Is the core of the orebody marginal value, or does it consist of high value rock?   Ultimately it will be the exploration company's task to keep drilling to define if there is sufficient tonnage of this higher value rock to justify a mine.  However this shows that at least the grades are there.

Intervals of Interest Example

The next series of plots examines the insitu rock values over drill intervals typically published in a company news releases. The intervals of interest will composite the individual assays over larger widths based on the company’s technical judgement.
It is interesting to see whether the larger intervals have good economic potential.   The following charts combine both major intervals with minor zones, often referred to as “including” in news releases. Both major and minor intervals can provide useful information.
Insitu Rock Value vs Depth:
This chart shows the rock values for multiple report intervals versus their depth (top) along the hole.
One can see multiple intervals at open pit depths (<250 m) with insitu values above the $20/t cutoff and above the $70/t threshold.
Within the upper 250 metres, we are seeing multiple intervals with good value.  That is a positive sign.
Note that these depths are not depths from surface, but distance along the drill hole.  In reality the intervals may be slightly closer to surface, depending on the hole inclination.
Polymetallic assay interval evaluation
Insitu Rock Value vs Interval Length:
The next question to ask is whether the higher value zones are narrow or wide?
In the example here one can see some wide zones (70 to 90m) with rock values in the range of $40-70/t.   These are good open pit mining widths.
There are numerous higher grade zones ($70-$200/t) in the 5m to 20m width range.   These widths are still fine for open pit mining.
Some intervals are quite narrow (<5m), being a bit more difficult to mine.  Since many of these are higher grade, they will tolerate some mining dilution.
Polymetallic assay interval evaluation

Conclusion

Although publishing insitu rock values is prohibited by NI-43-101, I find them important in my understanding the economic potential of a deposit. Reviewing the insitu rock values spatially is not difficult and can shed light on what is there. Even at a very early stage, one can get a sense of economic character of the orebody.   This is a great approach to use when doing an acquisition due diligence on an exploration stage project consisting mainly of drill hole data.
In my view, it would be beneficial if all polymetallic drill results were reported with the individual grades and using a standardized industry wide insitu rock value formula. Then one could compare projects (or even different zones on the same project) on an equal basis.   The cutoff to be applied to different projects would vary but the insitu value is what it is.
This might be better than each company applying their own unique equivalent grade calculation to their exploration results.
The equivalent grade calculation still requires assumptions on the metal prices and recoveries.  The result is, unfortunately, presented as a grade value rather than a dollar value.
The intervals of interest published in news releases are usually not available for download.   Great Bear is (was) one example where the data was available.  It would be nice if more companies followed suit by releasing their interval data in CSV or Excel format.  It worked out well for Great Bear!
Perhaps the detailed hole assay data may be too complex or voluminous to release.  Maybe this level of information is not useful except to the more technically driven investors. Nevertheless it would still be nice to have access to this drill data in electronic form, at least in the core of the orebody.
For further light reading, the two previous articles referenced above are “Gold Exploration Intercepts – Interesting or Not?" and "Metal Equivalent Grade versus NSR for multi-metals – Preference?"
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.   The entire blog post library can be found at https://kuchling.com/library/
Share

Mining Under Lakes – Part 2: Design Issues

This is Part 2 of a blog post related to open pit mining within bodies of water. Part 1 can be found at this link “Mining Under Lakes – Part 1“, which provides a few examples where this has been done successfully. Part 2  focuses on some of the social and technical issues the need to be considered when faced with the challenge of open pit mining within a water body.
dike construction in waterThe primary question to be answered is whether one can mine safely and economically without creating significant impacts on the environment.
The answer to this question will depend on the project location and the design of the water retaining structure.
I have worked on several projects where dike structures were built. I have also undertaken due diligence reviews of projects where dikes would be required. Most recently I have participated in some scoping level studies where mining within a lake or very close to a river were part of the plan.
In some instances, the entire orebody is located in the lakebed. In others, the orebody is mainly on land but extends out into the water. Each situation will be unique. In northern Canada, given the number of lakes present, it would be surprising if a new mining project isn’t close to a river or lake somewhere.

Dike concepts consider many factors

Different mining projects may use different styles of dikes, depending on their site conditions. Some dikes may incorporate sheet piling walls, slurry cutoff walls, low permeability fill cores, or soil grouting. There are multiple options available, and one must choose the one best suited for the site.
The following is list of some of the key factors and issues that should be examined.

ESG Issues

One’s primary focus should be on whether building a dike would be socially and environmentally acceptable. If it is not, then there is no point in undertaking detailed geotechnical site investigations and engineering design. One must have the “social license” to proceed down this path.
Water Body Importance: Is there a public use of the water body? It could be a fresh water source for consumption, used for agricultural or fishery purposes, or used as a navigable waterway, etc. Would the presence of the dike impact on any of these uses? Does the water body have any historical or traditional significance that would prevent mining within it?
Lake Turbidity: Dike construction will need to be done through the water column. Works such as dredging or dumping rock fill will create sediment plumes that can extend far beyond the dike. Is the area particularly sensitive to such turbidity disturbances, is there water current flow to carry away sediments?
At Diavik, a floating sediment curtain surrounding the dike construction area was largely able to contain the sediment plume in the lake.
Regional Flow Regime: Will the dike be affecting the regional surface water flow patterns? If the dike is blocking a lake outflow point, can the natural flow regime be maintained during both wet and dry periods?

Location Issues

If there are no ESG issues preventing the use of a dike, the next item to address is the ideal location for it.
Water depth: normally as the dike moves further away from land, both the water depth and dike length will increase. The water depth at the deepest points along the dike are a concern due to the hydraulic head differential created once the interior water pool is pumped out. The seepage barrier must be able to withstand that pressure differential, without leaking or eroding. A low height dike in shallow water may be able to use a simpler seepage cutoff system than a dike in deep water.
Islands: Are there any islands located along the dike path that can be used to shorten the construction length and reduce the fill volumes? Is there a dike alignment path that can follow shallower water zones?
Diavik open pit dikesPit wall setback: Given the size and depth of the open pit, how far must the dike be from the pit crest? Its nice to have 200 metre setback distance, but that may push the dike out into deeper water.
If the dike is too close to the pit, then pit slope failures or stress relaxation may result in fracture opening and increase the risk of seepage flows or catastrophic flooding. The pit wall rock mass quality will be the key determining factor in the setback distance.
Maximizing ore recovery: If the ore zone extends further out into the lake, maximizing ore recovery may require using a steep pit wall along the outer sections of the pit. This may require positioning haulroads with switchbacks along other sides of the pit rather than using a conventional spiral ramp layout.
At Diavik (see image), the A154 north open pit wall was pushed to about 60 metres of the dike to access as much of the A154N kimberlite ore as possible. Haulroads were kept to the south side of the pit.
It may be possible to recover even more ore by pushing out the dike even further. However, this may result in a larger and costlier dike or even require a different style of dike. There will be a tradeoff between how much additional ore is recovered versus the additional cost to achieve that. There will be a happy medium between what makes both technical sense and economic sense.

Design Issues

Once the approximate location of the dike has been identified, the next step is to examine the design of the dike itself. Most of the issues to be considered relate to the geotechnical site conditions.
Lakebed foundation sediments: What does the lakebed consist of with respect to soft sediments? Soft sediments can cause dike settlement and cracking, or mud-waving of fill material.
Will the soft sediments need to be dredged prior to construction, and if so, where do you dispose of this dredge slurry, and what impact will dredging have on the lake turbidity?
Lakebed foundation gravels: Are there any foundation gravel layers that can act as seepage conduits beneath the dike? If so, will these need to be sub-excavated, or grouted, or cut off with some type of barrier wall?  Sonic drilling, rather than core drilling, is a better way to identify the presence of open gravel beds.
Upper bedrock fracturing: Is the upper bedrock highly fractured, thereby creating leakage paths? If so, then rock grouting may be required all along the dike path to seal off these fractures.
Major faults: Are there any major faults or regional structures that could connect the open pit with the lake, acting as a source of large water inflow?. At Diavik, we attempted to characterize such structures with geotechnical drilling before construction. Upon review, I understand there was one such structure not identified, which did result in higher pit inflows until it was eventually grouted off.
Water level fluctuations: In a lake or river one may see seasonal water level fluctuations as well as storm event fluctuations. The height of the dike above the maximum water level (i.e. freeboard) must be considered when sizing the dike.
Ice scouring: In a lake or river that freezes over, ice loads can be an important consideration. During spring breakup as the ice melts, large sheets of ice can be pushed around and may scour or damage the crest of the dike. The dike must be robust enough to withstand these forces.
Construction materials available on site: Is there an abundance of competent rock for dike fill? Is there any low permeability glacial till or clay that can be used in dike construction? If these materials are available on site, the dike design may be able to incorporate them. If such materials are not available, then a alternate dike design may be more appropriate, albeit at a cost.

Conclusion

Each mine site is different, and that is what makes mining into water bodies a unique challenge. However many mine operators have done this successfully using various approaches to tackle the challenge.
Even at the exploration stage, while you are still core drilling the orebody through the ice, you can start to collect some of this information to help figure it all out.
The bottom line is that while mining into a water body is not a preferred situation, it doesn’t mean the project is dead in the water. It will add capital cost and environmental permitting complexity, but there are proven ways to address it.
On the opposite side, I have also seen situations where a dike solution was not feasible, so ultimately there are no guarantees that engineers can successfully address every situation. Lets hope your project isn’t one of them.
There could be a 3rd part to this post that discusses issues associated with underground mining beneath bodies of water; however that is not my area of expertise.  I would be more than happy to collaborate on a article with someone willing to share their knowledge and experience on that subject.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Mining Under Lakes – Part 1: Examples

Mining Under Lakes
Springpole Project

Springpole Project

I recently saw an investor presentation from First Mining Gold about their Springpole Project. The situation is that their open pit is located within a lake and will require the construction of a couple of small cofferdams to isolate the pit area from the lake. The concept is shown in this image.
Over the last couple of years I have been involved in a few early-stage studies for mining projects in which nearby bodies of water play a role in the design.    In Canada’s north there are thousands of lakes and rivers, so its not surprising to find mines next to them.
That got me thinking about how many other mines are in the same situation, i.e. projects that may be located very close to, or within, a lake, river, or ocean. Hence I have compiled a short list of a few such mines.
I have been directly involved with some of those in the list, while others are only known to me with limited detail. Some mines I had never heard of before, but their names were provided to me by some Twitter colleagues.
My observation is that building a mine within, or adjacent to, a body of water is nothing new and this has been done multiple times successfully.
Some of these projects may refer to the dams as “dikes”, “cofferdams”, “sea walls” but I assume they are all providing roughly the same function of holding back water for the life of the project.  They are not viewed as permanent dams.
This is Part 1 of a two-part blog post. Part 1 provides some examples of projects where water bodies were involved in the design. Part 2 provides a discussion on specific geotechnical and hydrogeological issues that would normally have to be examined with such projects.

Some Lake Mining Examples

The following are some examples of operating mines involving lakes. I have captured a few Google Earth images, unfortunately some have only low resolution vintage satellite imagery.

Diavik Diamond Mines, NWT

This is a project I was working on with in 1997 to 2000 while it was still at the design and permitting stage.  My role focused on pit hydrogeology and geotechnical as well as mine planning.
The project would require the construction of three dikes in sequence to mine four lakebed kimberlite pipes.
The three dikes were named after the associated kimberlite pipe being mined inside it; A154, A418, and A21.
The first dikes were built in 2002 and the last dike (A21) was completed in 2018.
The total dike length for the three dikes is about 6.2 km.
For those interested in learning a bit more about Diavik, I have posted an earlier article about the open pit hydrogeology there, linked to at " Hydrogeology At Diavik – Its Complicated".
Diavik mines

Gahcho Kue, NWT

This is a DeBeers diamond project was built in 2016 and required the construction of several small dikes to allow access for open pit mining.    The photos show the pre-mining situation and the site as it is today.   One can see the role the lake would play in the site layout and the need for multiple small dikes.
Gahcho Kue diamond mine

Meadowbank, NWT

This is an Agnico-Eagle gold mining operation built in 2010 that required a cofferdam to be built around one of their open pits (see image).
The total dike length is about 2000 metres.   I don't know much more about it than that unfortunately.
Meadowbank Mine

Cowal Gold Mine, Australia

Yes, a lake in Australia ! This is a former Barrick operation, now owned by Evolution Mining, and is another example where the mine is located within the shoreline of a lake (Lake Cowal).    I don't know much about this, the name was kindly provided to me by a colleague.
The total dike length appears to be about 3000 metres.
Cowal Gold Mine

Rabbit Lake Sask

The historical Rabbit Lake uranium mining operation required the construction of cofferdams around a few of their open pits.  They are now reclaimed and flooded.
Rabbit Lake uranium

St Ives Gold Mine, Australia

This is a unique situation in that several pits are located within an ephemeral (intermittent) salt lake and dikes were required to prevent pit flooding during wet season.
St Ives gold mine

Some River Mining Examples

The following are some examples of operating mines involving rivers.  Rivers provide a somewhat different design challenge since they have flowing water, who's volume and velocity may change seasonally.    Constrictions in the river created by the dike itself may increase the flow velocity and erosion potential.

Gorevsky Mine, Siberia

This lead-zinc operation has an orebody that extends into the Angara River.
This mine has built a fairly large cofferdam into the river, and is currently mining a large pit within it.  The total cofferdam length appears to be about 4000 metres.
It would be interesting to see how close the pit will get to the cofferdam.   We'll check back in a few years.
Gorevsky Mine

BHP Suriname Bauxite Mine

This is a project I was involved with several years ago.  The bauxite deposit extends beneath the Suriname River and the goal was to mine as much ore as possible.
Given the flow rates in the river, especially during the wet season, it would be difficult to maintain a cofferdam out into the river.
The shoreline overburden consisted of sands and soft clays, so the decision as made to construct a sheet piling wall along the river bank to protect the pit from river erosion.   This was mined out successfully and eventually reclaimed.
Suriname Bauxite Mine

McArthur River, Australia

In situations where the river (creek) is small enough and the topography allows, one can divert the entire river around the mine.
There are several examples of this in Canada and elsewhere.  Here’s the McArthur River lead-zinc mine in Australia, where they channeled their small river around the open pit.
McArthur river diversion

An Ocean Example

There are some examples of mining near the ocean. These operations may need to deal with large storm water level surges and large tidal fluctuations.   The Island Copper Mine on northern Vancouver Island is an example where they mined close to the shoreline but not actually into the ocean (as far as I am aware).

Cockatoo Island Mine, Australia

This interesting iron ore mine has an ore zone that dips 60 degrees, is 35 metres wide, with a strike length of more than one kilometre.
A sea wall was constructed to prevent any tidal water from entering the open pit that was to be mined, with reportedly high tidal fluctuations there.
Cockatoo iron mine

Conclusion

As one can see, the idea of mining into a body of water is nothing new.   Its not a preferred situation, but it can be done economically and safely.   The technical challenges are straightforward, and engineers have dealt with them before.  However there also are instances where the design could not economically address the water issue, and thus played a role in the mine not getting built.
If you know of other mines not listed above that have successfully dealt with a water body, please let me know and I can update this blog post.
This concludes Part 1.  Part 2 can be read at this link " Mining Under Lakes – Part 2: Design Issues" discusses some of the concerns that engineers need to consider when building a mine in these situations.

Pantai Remis tin mine

Finally, the worst-case scenario is shown in this grainy video of a tin mine (Pantai Remis Mine) pit slope failure.  It seems they mined too close to the ocean.  Watch to the end, its hard to believe. Its looks like something out of a Hollywood disaster movie.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.   The entire blog post library can be found at https://kuchling.com/library/
Share

NPV One – Cashflow Modelling Without Excel

NPV One mining software
From time to time, I encounter interesting software applications related to the mining industry.  I recently became aware of NPV One, an Australian based, cloud hosted application used to calculate mineral project economics. Their website is https://npvone.com/npvone/
NPV One is targeting to replace the typical Excel based cashflow model with an online cloud model. It reminds me of personal income tax software, where one simply inputs the income and expense information, and then the software takes over doing all the calculations and outputting the result.
NPV One may be well suited for those not comfortable with Excel modelling, or not comfortable building Excel logic for depreciation, income tax, or financing calculations. These calculations are already built in the NPV One application.
I had a quick review of NPV One, being given free access to test it out. I spent a bit of time looking at the input menus and outputs, but by no means am I proficient in the software after this short review.
Like everything, I saw some very good aspects and some possible limitations. However, my observations may be a bit skewed since I do a lot of Excel modelling and have a strong comfort level with it. Nevertheless, Excel cashflow modelling has its own pro’s and con’s, some of which have been irritants for years.

NPV One – Pros and Cons

NPV One mining softwarePros

  1. NPV One develops financial models that are in a standardized format. Models will be very similar to one another regardless of who creates it. We are familiar with Excel “artists” that have their own modelling style that can make sharing working models difficult. NPV One might be a good standard solution for large collaborative teams looking at multiple projects while working in multiple offices.
  2. NPV One, I have been assured, is error free. A drawback with Excel modelling is the possibility of formula errors in a model, either during the initial model build or by a collaborator overwriting a cell on purpose (or inadvertently).
  3. With NPV One, a user doesn’t need to be an Excel or tax modelling expert to run an economic analysis since it handles all the calculations internally.
  4. NPV One allows the uploading of large input data sets; for example life-of-mine production schedules with multiple ore grades per year. This means technical teams can still generate their output (production schedules, annual cost summaries, etc.) in Excel. They can then simply import the relevant rows of data into NPV One using user-created templates in CSV format.
  5. As NPV One evolves over time with more client input, functionality and usability may improve as new features are added or modified.

Cons

Like anything, nothing is perfect and NPV may have a few issues for me.
  1. Since I live and breathe with Excel, working with an input-based model can be uncomfortable and take time to get accustomed to. Unlike Excel, in NPV One, one cannot see the entire model at once and scroll down a specific year to see production, processing, revenue, costs, and cashflow. With NPV jump to. If you’re not an avid Excel user, this issue may not be a big deal.
  2. In Excel one can see the individual formulas as to how a value is being calculated.  Excel allows one to follow a mathematical trail if one is uncertain which parameters are being used. With NPV One the calculations are built in. I have been assured there are no errors in NPV One, so accuracy is not the issue for me. It’s more the lack of ability to dissect a calculation to learn how it is done.
  3. With NPV One, a team of people may be involved in using it. That’s the benefit of collaborative cloud software. However that means there will be a learning curve or training sessions that would be required before giving anyone access to the NPV One model.  Although much of NPV One is intuitive, one still needs to be shown how to input and adjust certain parameters.
  4. Currently NPV One does not have the functionality to run Monte Carlo simulations, like Excel does with @Risk. I understand NPV One can introduce this functionality if there is user demand for it. There will likely be ongoing conflict to try to keep the software simple to use versus accommodating the requests of customers to tailor the software to their specific needs.

Conclusion

The NPV One software is an option for those wishing to standardize or simplify their financial modelling.
Whether using Excel or NPV One, I would recommend that a single person is still responsible for the initial development and maintenance of a financial model. The evaluation of alternate scenarios must be managed to avoid it becoming a modelling team free for all.
Regarding the cost for NPV One, I understand they are moving away from a fixed purchase price arrangement to a subscription based model. I don’t have the details for their new pricing strategy as of May 2023. Contact Christian Kunze (ck@npvone.com) who can explain more, give you a demo, and maybe even provide a trial access period to test drive the software.
To clarify I received no compensation for writing this blog post, it is solely my personal opinion.
Regarding Excel model complexity mentioned earlier, I have written a previous blog about the desire to keep cashflow models simple and not works of art. You can read that blog at Mine Financial Modelling – Please Think of Others”.
As with any new mining software, I had also posted some concerns with QP responsibilities as pertaining to new software and 43-101. You can read that post at the appropriately titled “New Mining Software and 43-101 Legal Issues”.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/

 

Share

Steeper Pit Slopes Can Save Money

We likely have all heard the statement that increasing pit wall angles will result in significant cost savings to the mining operation.
What is the potential cost saving?
The steeper wall angles reduce waste stripping volumes, which also provide other less obvious benefits.
I was recently in a situation where we undertook some comparative open pit designs using both 45 and 50 degree inter-ramp angles (“IRA”). I would like to share some of those results and discuss where all the benefits may lay.

Comparative Pit Designs

In this project, four separate open pits were designed with 45 and 50 degree IRA’s in an area with hilly topography. Some of the pits had high walls that extended up the valley hillsides. Its not hard to envision that waste stripping reductions would be seen along those areas with steepened walls.
The results of applying the increased  inter-ramp angle to each of the four pits is shown in the Bar Chart. Note that the waste reduction is not necessarily the same for each pit.  It depends on the specific topography around each pit.
However, on average, there was an overall 15% reduction in waste tonnage.
The Table shown below presents the cumulative tonnage for all four pits. The 50 degree wall results in a waste decrease of 25.4 million tonnes (15%), with a strip ratio reduction from 5.8:1 to 5.0:1.
There is also a very minor decrease in ore tonnage. This is because the 50 degree slopes did lose some ore behind the walls that is being recovered by the 45 degree slope.
In both scenarios the project life would be about 10 years at an assumed ore processing rate of 3 Mtpa.

4 Positive Impacts of Steeper Walls

In general one can typically see four positive outcomes from adopting steeper pit walls. They are as follows:
1. Cost Savings: The waste tonnage reduction over the 10 year life would be about 25.4 million tonnes. At a mining cost of $2.00/tonne, this equates to $50.8 million tonnes spent less on stripping. This could move the project NPV from marginal to profitable, since most waste is normally stripped towards the front part of the mining schedule with less discounting.
The next time you are looking at the NPV from an open pit project, take a quick look to see if the pit slope assumptions are conservative or optimistic. That decision can play a significant role in the final NPV.
2. Equipment Fleet Size: Over the 10 year life, the average annual mining rate would range from 20.5 Mtpa (45 deg) to 18.1 Mtpa (50 deg). On a daily basis, the average would range from 56,100 tpd (45 deg) versus 49,700 tpd (50 deg). While this mining rate reduction is not likely sufficient to eliminate a loader, it could result in the elimination of a truck or two.   This would have some capital cost saving.
3. Waste Dump Size: The 15% reduction in the waste tonnage means external waste dumps could be 15% smaller. This may not have a huge impact but could be of interest if waste storage sites are limited on the property. It could have a more significant impact if local closure regulations require open pit backfilling.
4. Pit Crest Location: The steeper wall angles result in a shift in the final pit crest location. The Image shows the impact that the 5 degree steepening had on the crest location for one of the pits in this scenario.
Although in this project the crest location wasn’t critical, there are situations where rivers, lakes, roads, mine facilities, or public infrastructure are close to the pit.  A steeper wall could improve ore recovery at depth while maintaining the same buffer setback distance.

Conclusion

Steeper pit walls can have multiple benefits at an open pit mining operation. However, these benefits can all be negated if the rock mass cannot tolerate those steeper walls. Pit wall failures could be minor or they could have major impacts. There are the obvious worker safety issues, as well as equipment damage and production curtailment concerns with slope failures.  Public perception of the mining operation also comes into play with dangerously unstable slopes.
Steepening of the pit walls is great in theory, but always ensure that geotechnical engineers have confirmed it is reasonable.
It is relatively easy to justify spending additional time and money on proper geotechnical investigations and geotechnical monitoring given the potential slope steepening benefits.
When designing pits, there is some value in looking at alternate designs with varying slope angles to help the team understand if there are potential gains and how large they might be.
In closing, I previously wrote a related blog post about how pit walls are configured to ensure safe catch bench widths and decisions as to whether one should use single, double, or triple benching. That earlier post can be read at this link. Pit Wall Angles and Bench Widths – How Do They Relate?
Feel free to share your personal experiences if you are aware of other benefits (or even downsides) to steeper pit walls that I did not mention.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share

Life as an Engineer – Read All About It

One of the interesting aspects of being an engineer in the mining industry is travelling around the globe (or even) around your own country. I have been to over a dozen countries as part of my career and this only makes me a small-time traveller compared to other engineers I know. Travelling and experiencing the world is often part of the job, whether working for a junior miner, a major, a financial house, a consulting firm, or an equipment vendor. It is actually quite difficult to avoid travel if you work in mining.

Diavik Project

Recently a former colleague of mine on the Diavik Diamond Diavik project has published book that describes his life as an engineer. The book is titled Roseway: a Life of Adventure and is available on Amazon.
Its the story of John Wonnacott, a Canadian professional engineer who was involved in the construction of several projects, including the Diavik Diamond mine in Canada, a nickel smelter in China, a gold mine in Brazil, and a titanium mine in Madagascar to list a few.
John has a broad background, having conducted engineering studies in the jungles of Indonesia, the cold of Greenland, the sands of the desert, the heat of Australia, the altitude of the Andes. He has documented his engineering career in his new book.
Disclaimer: I have not yet read the book since it has only recently been published. However John has kindly sent me some excerpts that I have reprinted below to provide everyone with a sense for the content and style.

Some Excerpts

Introduction

At one time or another, I have been a professional paper-boy, forest worker, tree planter, market gardener, food processing equipment operator, lobster fisherman’s helper, commercial dragger deckhand, short-order cook, military engineering officer, computer system installer, greenhouse worker, permafrost researcher, marine oil spill cleanup specialist, pyrometallurgy researcher, garbage landfill operator, project manager, construction company general manager, regional director, open pit diamond miner, underground gold miner, corporate vice-president, design consultant, company owner, private corporation president and for 50 years, a damn good engineer. I have also been happily married to my wonderful wife Carole Anne for more than 52 years and we have 2 outstanding children. So I can add “husband”, “father” and “grandfather” to the list – but making lists like this is boring. Let me tell you my story.

Newfoundland

I remember in the late fall of that year, the company had a chance to bid on a larger project in Gros Morne National Park, Newfoundland. So our President, Frank Nolan (he was a brother to Fred Nolan, the infamous land-owner at Oak Island, by the way), decided he wanted to see the site and he chartered a Bell 106 helicopter to fly us there from Deer Lake. It was December (they say “December month” in that province) and when we got close to the Park, we ran into a sudden snow squall.
From bright sunny weather we were suddenly flying in heavy wet snow. I was sitting in the back of the chopper, with Frank sitting in the left front passenger seat. We were chatting with the pilot, via the radio headsets, when suddenly there was a loud “BEEP BEEP BEEP” sound coming from the front of the aircraft, and a number of the instrument lights started flashing. The engine had cut out – we learned later that wet snow had blocked the air intake and the engine had stalled – and we started descending pretty fast. Most people don’t realize that a helicopter will glide (quite steeply, at a glide angle of about 10 to 1) provided the pilot gets the torque off the rotor and he makes the correct feathering adjustments.
Our pilot did that instinctively and when we passed through the squall he calmly explained to us what was happening as he looked around for an open, flat spot to land. We didn’t have many options as we were flying over a densely wooded forest, with the mountains of Gros Morne and a deep fiord up ahead. But the pilot spotted a snow-covered frozen bog that was not a lot bigger than the helicopter and he put us down there as smoothly as if the engine hadn’t stopped. Maybe the deep snow cushioned our impact, because I felt nothing. But the instant we landed, Frank Nolan wrenched his door open, and he bolted out of the machine, straight ahead, in front of us.
The rotor was still spinning rapidly, and just as Frank ran ahead, the chopper settled further into the snow, tilting the machine forward in the process. With the chopper blades almost skimming the top of the snow, both the pilot and I expected Frank to be cut into pieces by the rotor, but he was just past their reach and he ran on, unaware of his narrow escape. When the spinning parts stopped, the pilot and I climbed out of the chopper to catch up with Frank. Examination of the machine showed us how the snow had plugged the air intake. The pilot cleared away the snow, and walked around the chopper once and then we took off again. We continued our aerial inspection of the National Park project and later that afternoon we flew back to Deer Lake.

Madagascar

The QMM field office In Port Dauphin, Madagascar was located near the edge of town, and I typically walked from my lodging to the office each morning when I was there, about the time when school started for the children. Typically I passed dozens and dozens of tiny bamboo huts with corrugated metal roofs, and dirt floors each about 2 meters square.
I was constantly amazed by the flocks of young boys and girls walking to school – each child aged from 6 to 15 years old, I suppose – dressed in immaculate white shirt or blouse and blue shorts or skirts. I never saw a dirty child, and how they could have kept clean clothes while living in those small crude huts was something I never could figure out. Even more amazing, were the genuine, wide smiles and frequent greeting as we passed the children: “bonjour monsieur, bonjour monsieur”.
It brings tears to my eyes even now, thinking about those children. If they were girls, they could look forward to a life expectancy of 48 years, according to the town officials we talked to. If they were boys, they could expect to live to an age of only 40 years. The perils of fishing in the ocean in dugout canoes made life even harder for the men.
The next morning, we arrived at the Astana international airport, to find that the check-in arrangements were quite different from what we were used to. Instead of checking our luggage at a desk and then walking through Security to get to our departure gate, everyone was expected to wheel their luggage and handbags through security, as the airline check-in desks were located inside.
The mechanics of rustling our luggage weren’t difficult, but as I passed through the check-point, suddenly a strange-sounding alarm went off. As the alarm rang and rang, my mind raced – what did I have in my bag that would trigger the alarm, I wondered? It didn’t help that the Security guards only spoke Russian, and they were dressed in military uniforms with ridiculously large military caps, which made them look imposing (and silly). But what began to worry me more, was that the look on the Security guards’ faces was not the usual one that happens when a piece of metal sets off an alarm. The guards looked frightened and angry, at the same time.
Fortunately for us, the commotion caught the attention of the clerks at the Turkish Airlines desk inside the terminal building, and one English-speaking fellow approached, speaking to the security guards in Russian first, then saying to us: “I speak English, may I help”? Well, he helped, but it took a while, because it turned out that a rarely used hidden nuclear radiation detector had been triggered when I came through the gate, and the guards were concerned that I had some kind of radioactive material in my suitcase.
For a moment my mind went blank, and then I remembered a card that I was carrying in my wallet. I had had a bout of prostate cancer the previous fall, and my brachytherapy treatment had involved inserting over a hundred tiny radioactive pellets in and around my prostate – designed to kill the cancer. The pellets decay naturally in a fairly short time, and by now, 9 or 10 months after my operation, I would have bet that the radioactive material had all decayed to an undetectable level. But my doctor had given me a card to carry, which explained the medical procedure, just for circumstances like this. When I pulled out the card, it was like a “Get out of Jail Free Card” from the Monopoly game. Instantly the guards’ attitudes changed from fear and suspicion, to sympathy and smiles. One of the big fellows wheeled my luggage over to the Turkish Airlines desk where the Good Samaritan clerk reverted back to his normal job of checking us in.

**** end of excerpt ****

Conclusion

It is one thing to briefly visit a remote project as part of a review team. It is another thing to be there as part of a design team trying to solve a problem and engineer a solution. I know of many engineers and geologists that would have similar work life experiences as part of their careers. However John has taken the initiative to write it all down.
The author is available to be contacted on LinkedIn if you have any questions or just want to say hello (at https://www.linkedin.com/in/john-wonnacott-84aa461a/).
The book can be found on Amazon at this link: Roseway: a Life of Adventure.
This is a story from the life of an experienced engineer working in the mining industry.  If you want to read the perspective from a new mining engineer graduate, check out this post “A Junior EIT Mining Story“.   There is no book deal yet here.
If you find stories about working as an engineer of interest, I have written a 2 part blog post on my adventures in the potash industry in Saskatchewan.  You can read that post at this link “Potash Stories from 3000 Feet Down – Part 1
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share