Articles tagged with: Mining

Vertical Conveyors Give Mining a Lift

There are not many things that are novel to me after having worked in the mining industry for almost 40 years.  However recently I came across a mining technology that I had heard very little about.  It’s actually not something new, but it has never been mentioned as a materials handling option on any project that I am aware of.
That innovative technology is vertical conveying. Not long ago I read about a vertical conveyor being used at the Fresnillo underground mine, hoisting 200 tph up from a depth of 400 metres and had a capital cost of $12.7 million.
I was aware of steep angle conveyors being used in process plants.  However they tended to be of limited height and have idlers and hardware along their entire length. Vertical conveyors are different from that.
After doing a bit of research, I discovered that vertical conveyors have been used since the 1970’s.  Their application was mainly in civil projects; for example in subway construction where one must elevate rock from the excavation level up to street level.   The mining industry is taking vertical conveyors to the next level.
I have never personally worked with vertical conveyors.  Therefore I am providing this discussion based on vendor information.  My goal is to create awareness to readers so that they might consider its application for their own projects.

How vertical conveying works

The background information on vertical conveying was provided to me by FKC-Lake Shore, a construction contractor that installs these systems.  FKC itself does not fabricate the conveyor hardware.  A link to their website is here.
The head station and tail station assemblies are installed at the top and bottom of a shaft.  The conveyor belt simply hangs in the shaft between these two points.  There is no need for internal guides or hardware down the shaft.   The conveyor belting relies on embedded steel cables for tensile strength and pockets (or cells) to carry the material.
The Pocketlift conveyor system is based on the Flexowell technology.  This has been advanced for deep underground applications with a theoretical lift height of 700 metres in one stage.   The power transfer is achieved by two steel cord belts that are connected with rigid cross bars. The ore is fed into rubber pockets, which are bolted onto the cross bars.    The standard Pocketlift can reaches capacities up to 1,500 m3/h and lift heights up to 700 m, while new generations of the technology may achieve capacities up to 4,000 m3/h.
The FLEXOWELL®-conveyor system is capable of running both horizontally and vertically, or any angle in between.  These conveyors consist of FLEXOWELL®-conveyor belts comprised of 3 components: (i) Cross-rigid belt with steel cord reinforcement; (ii) Corrugated rubber sidewalls; (iii) transverse cleats to prevent material from sliding backwards.   They can handle lump sizes varying from powdery material up to 400 mm (16 inch). Material can be raised over 500 metres with reported capacities up to 6,000 tph.

 

The benefits of vertical conveying

Vendors have evaluated the use of vertical conveying against the use of a conventional vertical shaft hoisting.    They report the economic benefits for vertical conveying will be in both capital and operating costs.
Reduced initial capital cost due to:
  • Smaller shaft excavation diameter,
  • Reduced cost of structural supports vs a typical shaft headframe,
  • Structural supports are necessary only in the loading and unloading zones and no support structures in the shaft itself since the belt hangs free.
Lower operating costs due to:
  • Significantly reduced power consumption and peak power demand,
  • Lower overall maintenance costs,
  • No shaft inspections required,
  • The belt is replaced every 8 – 10 years.

Conclusion

I consider vertical conveying as another innovation in the mining industry. There may be significant energy and cost benefits associated with it when compared to conventional shaft hoisting or truck haulage up a decline.
With raise boring, one can develop relatively low cost shafts for the vertical conveyor.  Hardware installation would be required only at the top and bottom of the shaft, not inside it.
The vendors indicate the conveying system should be able to achieve heights of 700 metres.  This may facilitate the use of internal shafts (winzes) to hoist ore from even greater depths in an expanding underground mine. It may be worth a look at your mine.
As stated earlier, I have no personal experience with vertical conveying. Undoubtedly there may be some negative issues associated with the system that I am currently unaware of.
I would appreciate anyone sharing their experience with these conveyors either in a civil application or a mining environment.   I will gladly update this blog article with additional observations or comments.
Update: for those interested in open pit applications for high angle conveyors, here is a recent article.  This is a 37 degree angle 3,000 tph sandwich belt, which is different than the vertical conveyors discussed above.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.   Follow me on Twitter at @KJKLtd for updates and insights.
Share

A Mining Career or a Travel Club

There have been some LinkedIn discussions about why the mining industry needs to attract more young people.  One of the selling points often mentioned is how mining gives a person the opportunity to experience the world.
Based on my own career, mining has definitely provided me with a chance to travel the world.  It will also help anyone overcome their fear of travel.   One will also learn that both international and domestic travel can be as equally rewarding.  There is nothing wrong with learning more about your own country.
The main purpose for my mining travel was due to either being a QP on a 43-101 study or visiting a site as a member of a due diligence team.   Other reasons have been to provide engineering support at a mine site or to meet with management teams for risk or strategy planning sessions.
Over the last year I haven’t traveled as much as in the past.  One reason is that not every QP working on a 43-101 report has to make a site visit. Fortunately, even when one doesn’t make a site visit, one still learns something about the local politics, legal system, infrastructure, and socio-economic situation in that country.
The map below shows places where I have been in my travels.  It also shows the locations of studies I was involved it. Mining really is a global business.   My map isn’t as cluttered as that of some geologists I know.  Exploration and resource geologists will visit many more destinations that an engineer will. After all, every project needs exploration drilling and a resource estimate, but not all projects advance to the engineering stage.

For those thinking of getting into mining, here is my list of pros and cons based on my own travel experience. Not everything is great about travel but some aspects of it can be fantastic.

What’s Good

  • I had the opportunity to visit many places for which there is a zero probability that I would have ever gone as a tourist.
  • Typically long duration long distance flights are in business class. You get lounge access and the perks associated with executive travel.   Less onerous short flights might be economy only, so be aware of your company policy.
  • All travel expenses, hotels, taxis, meals, etc. are paid for.  Just don’t get too exorbitant when wining and dining.  That’s the job of the senior person you are travelling with.
  • Upon arrival, often there will be a company representative to meet you at the airport.  They speak the local language and will take you where you need to go.  This saves you scrambling around an airport looking for a safe taxi to use.
  • You will get to meet local employees, go to dinner with them, travel around their country, and chat in the evenings. It’s a great way to learn about the people in the country you are visiting.
  • You will get to meet other technical people from around the world.  They might be expats working at a mine site or simply part of a multidisciplinary engineering team on the same visit.
  • You will be whisked away from tourist traps and thus have an opportunity to see the real countryside.
  • You will hit the ground running, get to visit mine sites, see some real live rocks, drill core, pit walls, equipment at work, and things happening.  You won’t get to see that while sitting in your downtown office.

What’s not so good

  • Unfortunately business trips are mostly of a very short duration since you’re not going there as a tourist.  You’re being paid for your time and expertise.

  • Mining trips are usually not to majors centers, so once arriving in the country you really haven’t arrived yet.  There might be more air flights or long pickup truck rides to get to the final destination. There can be a lot of waiting and the days can be long (and frustrating).   I remember on trip in northern Russia where four of us with luggage were jammed into a Volkswagen Rabbit in a snowstorm. That two hour trip took five hours, but we were just happy to make it back to the hotel.
  • Sometimes your accommodations will be less than stellar, i.e. one star hotels or tents.  So you’ll need to learn how to appreciate the charm of those places and not complain that it isn’t the Four Seasons Hotel.
  • Some travel locations can be potentially unsafe and require travelling security. That can lead to a bit of uneasiness.  I recall a trip to northern Mexico where we had two armed guards travelling with us.  I’m not sure if they were really needed and it was strangely more calming without them once they left.
  • Long east-west trips can leave you jet lagged and dog-tired. However the expectation is that at 7 am next morning you’re ready for breakfast and then head straight into the office.  You’re being paid to get to work, not to sleep.
  • The site visits will be focused on collecting or reviewing data and then immediately travelling back home to write your report.  Sightseeing opportunities can be limited other than what you will see during the course of your work. Sometimes you’ll get back home and think that you never really saw the place.

Conclusion

Business travel has always been one of the best parts of my mining career.   I can remember the details about a lot of the travel that I did.   Unfortunately the project details themselves will blur with those of other projects.
When I do travel now, it’s a nice change if just one flight gets you to your final destination.
During this Covid period, international travel is greatly restricted.  It will be interesting to see how soon things can return to normal, if they ever do.   To miss out on the travel aspect of a mining career would be a shame, unless the only travel you want to experience is sitting on public transit for a few hours each day.
By the way, my all time favorite place for a mining trip is…..Argentina.  It’s a long way from Toronto, but well worth it.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.   Follow me on Twitter at @KJKLtd for updates and insights.
Share

Heap Leach or CIL or Maybe Both

Typically gold mines consist of either a heap leach (HL) operation or a CIL type plant. There are a few projects that operate (or are considering) concurrent heap leach and CIL operations. Ultimately the mineral resource distribution determines if it makes economic sense to have both.  This blog discusses this concept based on past experience.
A CIL operation has higher capital and operating costs than a heap leach. However that higher cost is offset by achieving improved gold recovery, perhaps 20-30% higher. At higher gold prices or head grades, the economic benefit from improved CIL recovery can exceed the additional cost incurred to achieve that recovery.

Some background

Several years ago I was VP Engineering for a Vancouver based junior miner (Oromin Expl) who had a gold project in Senegal. We were in the doldrums of Stage 3 of the Lassonde Curve (read this blog to learn what I mean) having completed our advanced studies. Our timeline was as follows.
Initially in August 2009 we completed a Pre-Feasibility Study for a standalone CIL operation. Subsequently in June 2010 we completed a Feasibility Study. The technical aspects of Stage 2 were done and we were entering Stage 3. Now what do we do? Build or wait for a sale?
The property’s next door neighbor was the Teranga Sabodala operation. It made sense for Teranga to acquire our project to increase their long term reserves. It also made sense for a third party to acquire both of us. The Feasibility Study also made the economic case to go it alone and build a mine.
While waiting for various third-party due diligences to be completed, the company continue to do exploration drilling. There were still a lot of untested showings on the property and geologists need to stay busy.
Two years later in 2013 we completed an update to the CIL Feasibility Study based on an updated resource model. Concurrently our geologists had identified seven lower grade deposits that were not considered in the Feasibility Study.
These deposits had gold grades in the range of 0.5 to 0.7 g/t compared to 2.0 g/t for the deposits in the CIL Feasibility Study. We therefore decided to also complete a Heap Leach PEA in 2013, looking solely on the lower grade deposits.
These HL deposits were 2-8 km from the proposed CIL plant so their ore could be shipped to the CIL plant if it made economic sense. Test work had indicated that heap leach recoveries could be in the range of 70% versus >90% with a CIL circuit. The gold price at that time was about $ 1,100/oz.
Ultimately our project was acquired by Teranga in the middle of 2013.

Where should the ore go?

With regards to the Heap Leach PEA, we did not wish to complicate the Feasibility Study by adding a new feed supply to that plant from mixed CIL/HL pits. The heap leach project was therefore considered as a separate satellite operation.
The assumption was that all of the low grade pit ore would go only to the heap leach facility. However, in the back of our minds we knew that perhaps higher grade portions of those deposits might warrant trucking to the CIL plant.
For internal purposes, we started to look at some destination trade-off analyses. We considered both hard (fresh rock) and soft ore (saprolite) separately. CIL operating costs associated with soft ore would be lower than for hard ore. Blasting wasn’t required and less grinding energy is needed. The CIL plant throughput rate could be 30-50% higher with soft ore than with hard ore, depending on the blend.
I have updated and simplified the trade-off analysis for this blog. Table 1 provides the costs and recoveries used herein, including increasing the gold price to $1500/oz.
The graph shows the profit per tonne for CIL versus HL processing methods for different head grades.
The cross-over point is the head grade where profit is better for CIL than Heap Leach. For soft ore, this cross-over point is 0.53 g/t. For hard ore, this cross over point is at 0.74 g/t.
The cross-over point will be contingent on the gold price used, so a series of sensitivity analyses were run.
The typical result, for hard ore, is shown in Table 2. As the gold price increases, the HL to CIL cross-over grade decreases.
These cross-over points described in Table 2 are relevant only for the costs shown in Table 1 and will be different for each project.

Conclusion

It may make sense for some deposits to have both CIL and heap leach facilities. However one should first examine the trade-off for the CIL versus HL to determine the cross-over points.
Then confirm the size of the heap leach tonnage below that cross-over point. Don’t automatically assume that all lower grade ore is optimal for the heap leach.
If some of the lower grade deposits are further away from the CIL plant, the extra haul distance costs will tend to raise their cross-over point. Hence each satellite pit would have its own unique cross-over criteria and should be examined individually.
Since Teranga complete the takeover in mid 2013, we were never able to pursue these trade-offs any further.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and insights.
Share

Mining’s Lassonde Curve – A Wild Ride

Normally I don’t write about mining stock markets, preferring instead to focus on technical matters.  However I have seen some recent discussions on Twitter about stock price trends.  For every stock there are a wide range of price expectations.  Ultimately some of the expectations and realizations can be linked back to the Lassonde Curve.
The Lassonde Curve has been touted by many as a realistic representation of the life stages of a junior mining company.  The curve can sometimes be a roller coaster ride for company management.
Pierre Lassonde, was one of the founders of Franco-Nevada, the first gold royalty company. Thirty years ago he created his curve, that has now become a foundation in the junior mining business.  The Lassonde Curve outlines the company life stages, beginning at exploration and ending at production.  It shows the perceived value (i.e. stock value) that investors may assign at each life stage.
The stock price trend illustrated by the curve can, knowingly or unknowingly, impact on a company’s decision making process.  So in effect, there are some technical ramifications from it.
People may have differing opinions on what factors are driving the curve.   Take a look at it and decide for yourself. Typically people define the curve into four life stages, but I tend to view it in five stages.

Mining Company Stages 1 to 5

Stage 1 Climb

Stage 1 is the earliest stage, consisting of exploration.  This period generates rising anticipation from promotion and exciting press releases. The stock value climbs as the perceived value of the insitu geology increases.  Great Bear is an example of company currently in Stage 1 (as of June 2020), and appears to be in no hurry to exit from Stage 1.
Stage 2 is when the prospect moves into technical evaluation.  In other words, the engineers now climb aboard the ride.  This stage encompasses the PEA, PFS, and FS studies. Each of these can take months to complete, meantime new information releases may be lacking.
If the stock value declines, perhaps its because the engineers bring reality into the picture.  Investors may see that the project isn’t as easy or great as they anticipated during Stage 1.
Companies can also lose some presence in the market with no new news. Investors may begin looking at other companies that are still in Stage 1 and hence sell their shares.
Some companies may try to shorten Stage 2 and even skip over Stage 3 by going from a PEA directly into Stage 4 construction.
Stage 3 is the period when the studies have largely been completed and a production decision is pending.  At this time the company will be seeking strategic partners and project funding.  Permitting is also underway.  Unfortunately a lack of financing or poor permitting efforts will extend the time in Stage 3, which can extend for decades or even perpetuity. It’s easy to rattle off the names of companies sitting in Stage 3; for example Donlin Creek, Casino, KSM, and Galore Creek. It seems that once locked in a prolonged Stage 3, it can be difficult to get out of it.  Company promotion and marketing can be difficult.
Stage 4 begins when the financing is done and construction begins.  This is a sign that the project has been figured out, permits approved, and third-party due diligence found no fatal flaws.  The stock value may increase on this positive news, especially if construction is on time and on budget. Its even better news if it’s a period of rising commodity prices.
Stage 5 is the start-up and commercial production period, possibly nerve-racking for some investors. This is where the rubber hits the road. The stock price can fall if milled grades, operating costs, or production rates are not as expected.
Investors may need to decipher press releases to figure out if things are going well or not.  Some investors may now bail out at this time to companies in Stage 1 for greater upside (the 10 bagger).

Companies Staying front and center

Companies know that investors can move elsewhere at any time, so they will try to address the Stage 2 and Stage 3 doldrums in different ways.   They can:
  • Find new exploration prospects elsewhere while the engineering work is underway.
  • Undertake a series of optimization studies on the same project to keep up the news flow.
  • Continue step out drilling on the same property to expand resources and generate new excitement.
  • Have management appear regularly on podcasts, webinars, conferences, and keep promoting on LinkedIn, Twitter, and with newsletter writers.
Ideally one would like to stagger multiple prospects at different stages of the Curve. While this makes sense, it also takes a fair bit of funding to do it.   It also may bring criticism that the company is losing focus on their flagship project.  Generally if the stock price is improving, you don’t see this complaint.

Conclusion

In closing, I just wanted to present the Lassonde Curve for those who may not have seen it before. For those playing the junior stocks, it may help explain why their prices fluctuate for essentially the same project.  For some companies, the curve can be a wild ride.
Some corporate presentations will highlight the Lassonde Curve, particularly when they are rising in Stage 1.  You are less likely to see the curve presented when they are rolling along in Stages 2 or 3.
Some say the Curve relates to the de-risking of a project as it advances, with risks shifting from exploration related to development related.   That may be true, but I suggest the curve is simply based on investor perception and impatience.
The ability to promote oneself and stay relevant in the market plays a key role in defining the shape of a company’s curve.
As a final note, people looking at the Lassonde curve often focus on the rise and dip in the middle part. There is less focus on what happens on the far right side of the graph as it trends into the future. There is an often (but forgotten) dip there too.
Another interesting aspect of the junior mining industry is how the herd mentality and fear of missing out is standard operating policy.  Companies will rush into areas, acquire whatever ground they can, as long they can tout it as being a certain commodity project.   And its not only commodities that generate excitement; its also locations and technologies.  Read more at the blog post “Mining Fads and the Herd Mentality“.
The entire blog post library can be found at this LINK with topics ranging from geotechnical, financial modelling, and junior mining investing.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.   Follow us on Twitter at @KJKLtd for updates and insights.
Share

Climbing the Hill of Value With 1D Modelling

Recently I read some articles about the Hill of Value.  I’m not going into detail about it but the Hill of Value is a mine optimization approach that’s been around for a while.  Here is a link to an AusIMM article that describes it “The role of mine planning in high performance”.  For those interested, here is a another post about this subject “About the Hill of Value. Learning from Mistakes (II)“.
hill of value

(From AusIMM)

The basic premise is that an optimal mining project is based on a relationship between cut-off grade and production rate.  The standard breakeven or incremental cutoff grade we normally use may not be optimal for a project.
The image to the right (from the aforementioned AusIMM article) illustrates the peak in the NPV (i.e. the hill of value) on a vertical axis.
A project requires a considerable technical effort to properly evaluate the hill of value. Each iteration of a cutoff grade results in a new mine plan, new production schedule, and a new mining capex and opex estimate.
Each iteration of the plant throughput requires a different mine plan and plant size and the associated project capex and opex.   All of these iterations will generate a new cashflow model.
The effort to do that level of study thoroughly is quite significant.  Perhaps one day artificial intelligence will be able to generate these iterations quickly, but we are not at that stage yet.

Can we simplify it?

In previous blogs (here and here) I described a 1D cashflow model that I use to quickly evaluate projects.  The 1D approach does not rely on a production schedule, instead uses life-of-mine quantities and costs.  Given its simplicity, I was curious if the 1D model could be used to evaluate the hill of value.
I compiled some data to run several iterations for a hypothetical project, loosely based on a mining study I had on hand.  The critical inputs for such an analysis are the operating and capital cost ranges for different plant throughputs.
hill of valueI had a grade tonnage curve, including the tonnes of ore and waste, for a designed pit.  This data is shown graphically on the right.   Essentially the mineable reserve is 62 Mt @ 0.94 g/t Pd with a strip ratio of 0.6 at a breakeven cutoff grade of 0.35 g/t.   It’s a large tonnage, low strip ratio, and low grade deposit.  The total pit tonnage is 100 Mt of combined ore and waste.
I estimated capital costs and operating costs for different production rates using escalation factors such as the rule of 0.6 and the 20% fixed – 80% variable basis.   It would be best to complete proper cost estimations but that is beyond the scope of this analysis. Factoring is the main option when there are no other options.
The charts below show the cost inputs used in the model.   Obviously each project would have its own set of unique cost curves.
The 1D cashflow model was used to evaluate economics for a range of cutoff grades (from 0.20 g/t to 1.70 g/t) and production rates (12,000 tpd to 19,000 tpd).  The NPV sensitivity analysis was done using the Excel data table function.  This is one of my favorite and most useful Excel features.
A total of 225 cases were run (15 COG versus x 15 throughputs) for this example.

What are the results?

The results are shown below.  Interestingly the optimal plant size and cutoff grade varies depending on the economic objective selected.
The discounted NPV 5% analysis indicates an optimal plant with a high throughput (19,000 tpd ) using a low cutoff grade (0.40 g/t).  This would be expected due to the low grade nature of the orebody.  Economies of scale, low operating costs, high revenues, are desired.   Discounted models like revenue as quickly as possible; hence the high throughput rate.
The undiscounted NPV 0% analysis gave a different result.  Since the timing of revenue is less important, a smaller plant was optimal (12,000 tpd) albeit using a similar low cutoff grade near the breakeven cutoff.
If one targets a low cash cost as an economic objective, one gets a different optimal project.  This time a large plant with an elevated cutoff of 0.80 g/t was deemed optimal.
The Excel data table matrices for the three economic objectives are shown below.  The “hot spots” in each case are evident.

hill of value

hill of value

Conclusion

The Hill of Value is an interesting optimization concept to apply to a project.  In the example I have provided, the optimal project varies depending on what the financial objective is.  I don’t know if this would be the case with all projects, however I suspect so.
In this example, if one wants to be a low cash cost producer, one may have to sacrifice some NPV to do this.
If one wants to maximize discounted NPV, then a large plant with low opex would be the best alternative.
If one prefers a long mine life, say to take advantage of forecasted upticks in metal prices, then an undiscounted scenario might win out.
I would recommend that every project undergoes some sort of hill of value test, preferably with more engineering rigor. It helps you to  understand a projects strengths and weaknesses.  The simple 1D analysis can be used as a guide to help select what cases to look at more closely. Nobody wants to assess 225 alternatives in engineering detail.
In reality I don’t ever recall seeing a 43-101 report describing a project with the hill of value test. Let me know if you are aware of any, I’d be interested in sharing them.  Alternatively, if you have a project and would like me to test it on my simple hill of value let me know.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Simple Financial Models Can Really Help

A few years ago I posted an article about how I use a simple (one-dimensional) financial model to help me take a very quick look at mining projects. The link to that blog is here. I use this simple 1D model with clients that are looking at potential acquisitions or joint venture opportunities at early stages. In many instances the problem is that there is only a resource estimate but no engineering study or production schedule available.

By referring to my model as a 1D model, I imply that I don’t use a mine production schedule across the page like a conventional cashflow model would.
The 1D model simply uses life-of-mine reserves, life-of-mine revenues, operating costs, and capital costs. It’s essentially all done in a single column.  The 1D model also incorporates a very rudimentary tax calculation to ballpark an after-tax NPV.
The 1D model does not calculate payback period or IRR but focuses solely on NPV. NPV, for me, is the driver of the enterprise value of a project or a company. A project with a $100M NPV has that value regardless of whether the IRR is 15% or 30%.

How accurate is a 1D model?

One of the questions I have been asked is how valid is the 1D approach compared to the standard 2D cashflow model. In order to examine that, I have randomly selected several recent 43-101 studies and plugged their reserve and cost parameters into the 1D model.
It takes about 10 minutes to find the relevant data in the technical report and insert the numbers. Interestingly it is typically easy to find the data in reports authored by certain consultants. In other reports one must dig deeper to get the data and sometimes even can’t find it.
The results of the comparison are show in the scatter plots. The bottom x-axis is the 43-101 report NPV and the y-axis is the 1D model result. The 1:1 correlation line is shown on the plots.
There is surprisingly good agreement on both the discounted and undiscounted cases. Even the before and after tax cases look reasonably close.
Where the 1D model can run into difficulty is when a project has a production expansion after a few years. The 1D model logic assumes a uniform annual production rate for the life of mine reserve.
Another thing that hampers the 1D model is when a project uses low grade stockpiling to boost head grades early in the mine life. The 1D model assumes a uniform life-of-mine production reserve grade profile.
Nevertheless even with these limitations, the NPV results are reasonably representative. Staged plant expansions and high grading are usually modifications to an NPV and generally do not make or break a project.

Conclusion

My view is that the 1D cashflow model is an indicative tool only. It is quick and simple to use. It allows me to evaluate projects and test the NPV sensitivity to metal prices, head grades, process recovery, operating costs, etc. These are sensitivities that might not be described in the financial section of the 43-101 report.
This exercise involved comparing data from existing 43-101 reports. Obviously if your are taking a look at an early stage opportunity, you will need to define your own capital and operating cost inputs.
I prefer using a conventional cashflow model approach (i.e. 2D) when I can. However when working with limited technical data, it’s likely not worth the effort to create a complex cashflow model. For me, the 1D model can work just fine. Build one for yourself, if you need convincing.
In an upcoming blog I will examine the hill of value optimization approach with respect to the 1D model.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Connecting With Investors – Any New Ideas?

I recently read some LinkedIn posts from junior mining executives and IR staff asking for ideas about new ways to engage with investors.  The commonly used ways rely on PowerPoints, webinars, and trade show booths.   However during this Covid-19 crisis, trade shows are no longer an option.  Therefore these face to face discussions with investors will now be missing.  This will impact on the ability of a company to connect with and establish trust with those people.

What else can be done?

Perhaps with technology, like Zoom, one can replicate the personal feel of a trade show booth. One can still have back and forth conversations with investors rather than just doing lecture style webinars.
Free discussion is good in most cases. Letting investors feel they are sitting around a table will give them a better understanding of how management thinks and how decisions are being made.  It will also help them get to know the personality of the management team.
I’m not an IR person but I admire the job they have to do, especially in today’s business environment.  I have recently sat in on several junior mining online webinars.  When listening to the Q&A’s afterwards, it is apparent that many attendees enjoyed understanding the technical aspects of a project.  However they will only get that understanding by asking questions.  Trade show booths gave them that opportunity.

Technology gives some options.  Like what?

Set up regularly scheduled Zoom meetings, enabling investors to have interactive back and forth conversations with management.  Try to avoid long presentations with questions only at the end. Have a moderator review and ask questions as they come in.
Management teams should introduce more than just the CEO or COO.  Include VP’s of geology, engineering, corporate development, from time to time.    Don’t hesitate to let the public meet more of your team.  Trade show booths are often manned by different team members.
Pick different topics for discussion on each conference call to avoid repeating the same PowerPoint over and over again.
Avoid being too scripted.
For example one call could be a fly-around of the property using Google Earth.  Another call could focus on the ore body and resource model.  Another call might discuss metallurgy and the thought process behind the flow sheet. Perhaps discuss the development options you have considered.
None of this information is likely confidential if it has been presented in your 43-101 report.
Companies file highly technical 43-101 reports on SEDAR, but then let the investors fend for themselves.   One could take some online time for high level walk through of the report.  Clearly explain technical issues and how they have been addressed or will be addressed in the future.  This is an opportunity to explain things in plain English, and field questions.
One downside to such calls is if there are significant flaws with a project.  Open discussions may help expose them.   One needs to know your own project well, be aware of all the issues, and have them under control in one way or another.

Conclusion

Better communication with investors can increase confidence in a management team.   Although some investors may not enjoy technical discussions, I think there is a subset that will find them very helpful and interesting.  There will likely be an audience out there.
Mining projects are complex with many moving parts and many uncertainties. Trust and confidence will come if a company is transparent in what they are doing and explain why they are doing it.
The mining industry is looking for new ways to reach out, so it shouldn’t be afraid to try new things. Some management teams will be great at it, others not so much.  Figure out where you fit in.
Unfortunately one of the aspects of trade shows that cannot be replicated is the ability for investors to wander around aimlessly, take a quick glance at a lot of companies, and then decide which ones they want to learn more about.

Warning: zoom bombing

As an aside, if you are using Zoom make sure the host has configured the right settings.  There are instances where anonymous participants can suddenly share their own computer screen, i.e. with questionable videos, to the group.  It’s been referred to as “zoom bombing”.
Read more about how to prevent zoom bombing at the following two links.
https://www.forbes.com/sites/leemathews/2020/03/21/troll-terrifies-zoom-meeting-zoombombing/#2765abfc3e70
https://www.businessinsider.com/zoom-settings-change-avoids-trolls-porn-2020-3
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.   
Follow me on twitter (@KJKLtd) or LinkedIn at https://www.linkedin.com/in/kenkuchling/)
Share

Consultants Have to Earn a Living Too

The number of independent mining consultants is increasing daily as more people reach retirement age or are made redundant.
Nowadays it seems everyone is gradually becoming a self-employed consultant. Possibly that is because retirees need the money.  Maybe they need something post-career to keep them occupied.
Here are a couple of lesser known ways to generate income for those of you choosing this new career path.
One of these has been around for awhile while the other is relatively new.  I only have personal experience with one of them.

GLG – Give me an hour

GLG (https://glg.it/) is one of several information services that provide short term consulting assignments.  By short term, I mean 1 to 2 hours long.
GLG has been around for many years providing a platform for connecting those seeking information with those who have it.
Typically someone, like an industry analyst, poses a question that gets sent out to relevant experts.
The question could be something like “XX Mining Company owns the Bonanza mine and our client would like to learn more about that operation including reserves and operating costs”.
Anyone who has the requisite knowledge can accept the consultation and submit their credentials for review.  If you’re selected, such consultations take place very soon.  They can be for 1 to 2 hours and pay $200 to $500 dollars.  GLG are very strict that rumors or confidential information are not disclosed during any of the consultations.  Only public information is to be used.
Since I have a background in potash, I am often issued potash industry related requests.  Questions posed might be “Can you describe the Saskatchewan potash industry, including operations, expansions, marketing plans, and operating costs”.  That’s a heck of a lot of information to provide in a 1 to 2 hour time frame for $400.   Likely very few people would possess all of that knowledge.   I assume their approach is to consult with several different experts and eventually piece together the puzzle.
Check out the GLG website. It’s free to sign up as an expert and maybe you’ll get yourself an assignment. I think there is even a reward for referrals (which I assume I will get shortly).

Digbee – What’s wrong now?

Digbee (https://thedigbee.com/) is a relatively new online venture that I’ve not yet used.  It is essentially a due diligence platform where one can hire experts to undertake targeted due diligence studies.
Furthermore any expert can prepare an independent review on a topic of their choice and then offer it up for sale.
The typical report costs $1,640 to $4,680 dollars.   As of March 2020, they have 13 reports for sale and 5 more in the pipeline.  Here’s a brief explainer video from the founder
The report list can be seen at this link.  The reports appear to be focusing on potential technical flaws in a project. Some titles are listed below.
  • Sample recoveries at shallow depths is a concern, this is not helped by the total lack of QAQC data” an analysis of Bomboré ($4,680)
  • Has the extensive testwork at Bomboré finally found an optimum process to proceed to development?” ($4,680)
  • Alpala’s technical merits and compares its cost estimate to other block caving development projects.” ($3,120).
  • Cerro Blanco’s very complicated geology in Guatemala may mean more expensive mining techniques will be required.” ($4,680)
  • Epithermal geologist raises questions on the reliability of the low grade resource at DeLamar.” ($3,120)
  • What impact does serpentinisation have on the confidence of recovered grade at RNC’s Dumont project?” ($4,680)
I’m not sure how many report copies each consultant will be able to sell .  However a click-bait title may help sell at least one copy.  That would be to the company the report is about.   Perhaps major investors or financial analysts will also buy a copy.
So if you have some free time, pick a project that’s on your radar and write a review.   It appears that you’ll get a 50% share of the revenue.    To learn more, read an article at this link.
I’m curious if the Digbee platform will continue to grow.  It’s unique to see independent research identifying potential issues with mining projects. Someone jokingly mentioned that these are the anti-newsletter writers.  I’m also curious to see how long before the lawyers and lawsuits begin to show up.
Given the relatively low price for these reports, I think one might make a lot more money (from TMZ) if one wrote a report titled “Famous Hollywood starlet has scandalous affair with mining company CEO”.

Conclusion

If you’re becoming an independent consultant, check out these two revenue channels.   They are tailor made for our growing numbers.
Follow me on twitter (@KJKLtd) or LinkedIn at https://www.linkedin.com/in/kenkuchling/)
Share

Benchmarking – Let’s See More Of It

Benchmarking is the process of measuring performance of a company’s attributes against those of another. Ideally the benchmarking comparison is made against what are considered to be the best in the industry.  Sometimes however the comparison is simply made between industry peers.
We often see junior mining companies benchmarking themselves against others. Sometimes corporate presentations provide graphs of enterprise value per gold ounce to demonstrate that a company might be undervalued.
We also see cash cost charts (an example to the right) benchmarking where a company’s production cost will rank among its competitors.
I view benchmarking as a great thing. The information can be very insightful, but with the caveat that it takes effort to ensure the comparative data is accurate.

Can we see more benchmarking?

Given the benefits of benchmarking, another area that might warrant such effort is related to capital cost estimates.
When a project moves into the development stage, the first two observable metrics are the construction progress and the capital cost expenditures. The capital cost trend is generally given very close scrutiny since it is a key indicator describing where a project is heading.
Lenders may have observers at site monitoring both construction progress and cash expenditures. Shareholders and analysts are watching for news releases that update the capital spending. Their concern is well founded due to several significant cost over-run instances.
Some of these over-runs have been fatal whereby the company has been unable to secure additional financing for the extra costs. There are others instances where a financing white knight has come in and essentially wrestled company ownership away from current shareholders.
Some industry people also feel that capital cost performance can foreshadow a project’s performance once it goes into commercial production.
Capital cost over-runs may be caused by poor execution and/or unforeseen events, or due to inaccurate cost estimation to begin with.  Many investors still have apprehension with capital cost estimates from advanced studies. This is where benchmarking may play a role. Mining company shareholders may want to see a comparison of their project capital cost with other similar projects.

Project databases

It would be a good thing if the mining industry (or other concerned parties) work together to create open source project databases. These would incorporate summary information and cost information for global mining projects.  The information is already out there, it just needs to be compiled.
One nice thing is that younger workers coming into the mining industry exhibit an interest in collaboration and information sharing. Hence maintaining the databases could be done by interested parties, industry experts, and/or crowd sourcing.
The databases would be public domain accessible to everyone and  could be used to benchmark a project against other similar projects.  The Global Tailings Portal (tailing.grida.no/about) is working to build a freely accessible database for the thousands of tailings dam globally. Its the same idea.
I realize that many mining projects are unique with site specific features and conditions. However many projects are also very similar to one another. For example West African gold projects in many cases can be replicates of one another with similar capital costs.
Published technical reports could include a chapter on benchmarking, whereby a project is compared with other similar projects. A company could provide rationale why their project will be costlier (or less expensive) than the others.

Conclusion

Benchmarking can be a great tool when done correctly. Benchmarking  capital costs might bring more transparency to the project development process. It may help convince nervous investors that the proposed costs are reasonable.
We already see corporate presentations using benchmarking, so why stop at production costs and share price valuation.
One could expand the reach to include operating costs but internal confidentiality may be an issue.  Furthermore operating costs are longer in duration and subject to change with global influences.
Capital cost accuracy is one of the primary concerns in the development of new projects. Possibly more benchmarking is part of the solution.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Consulting and Stock Compensation

The other day a press release came across my desk with the following title “First Mining Issues First Tranche Of Shares To Ausenco; Pre-Feasibility Study For Springpole Gold Project Underway”.
Reading it further, it was apparent that their study consultant, Ausenco, was being paid in company stock in lieu of cash.  The arrangement included an initial financing of $750k with a further $375k to follow once the pre-feasibility study was 75% complete.  Upon completion of the study another share payment was due.
That press release was interesting. I personally had never seen one like this before.
Some may see independence as an issue with their fiscal arrangement. Maybe… but this blog isn’t about the need for independent QP’s.  In fact I don’t recall feasibility studies having that requirement.  Some 43-101 resources estimates do require independence.
An industry discussion about where independence is required would be an interesting exercise.  However I will leave that conversation for a future post.

Would you work for company shares only?

I have never been in a situation where I was consulting with  company shares as my compensation.  Neither have I ever managed a study where outside consultants were being paid in shares.   However I can see the possibility of interesting dynamics at play.
In the past I have worked as an owner’s study manager and been awarded stock options along with salary.  In that role, my job was to look after the owner’s interests, pushing for cost efficiencies and optimizations.
Regarding share compensation, there are significant risks on the consultant’s side when they agree to be paid in shares.   I can see both positive and negative aspects with that type of a relationship.
I am not passing judgement here on what is right or wrong.  My objective is to comment on some basic issues that may arise.

Pro’s and Con’s

The positive aspects one might experience include;
  • It’s easier for the company to pay for the study since there are no cash outlays from the treasury.
  • The consultants might have the company’s best interests at heart since they will now be part owners of the company.
  • Possibly there will be greater technical effort to produce optimal designs and cost estimating efficiencies in the drive for great economics.
The potential pitfalls of this approach might include;
  • A public perception that the study is not impartial.
  • There is an overhang of shares that may be dumped onto the market in the near future.
  • Possibly the consultant will charge a premium for their services due to the financial risks they are taking.
  • The company may be more tolerable of study cost overruns since there is no hard cash outlay.
Regarding the first item “impartiality”, in the past there have been questions raised about the impartiality of engineering firms. I first recall reading this claim many years ago in a public response to a mining EIA application. Unfortunately I cannot find the exact source now.
The concern was whether the consultant’s work would be overly optimistic, seeing that they would eventually gain as a project moved from PEA through to the PFS and FS stages. They didn’t want to kill the golden goose. The project’s opponents were making the argument to the regulators “don’t believe what the engineering company is telling you”.
I’m curious how many times this argument has been used, seeing that it’s been around for some time.

Conclusion

It would be interesting to know how many consulting firms would be willing to accept compensation solely in shares.  Stock prices move up and down and the outcome of the study itself can have an impact on  share performance.
Unlike being paid in bitcoin, which also fluctuates in value, shares will generally have a hold period before they can be sold off.  This further increases the consultant’s risk.
I am curious to see whether the First Mining + Ausenco financial arrangement will create a precedent. Possibly it happens more than I am aware of.  Realistically I don’t see anything wrong with the approach, although one needs to understand the perceptions that it can create.   See where you sit if you were on the owner’s or consultant’s side and this idea was being discussed.  What would you do?
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share