Articles tagged with: Study Management

Power Generation & Desalinization – An Idea that Floats

Access to a fresh water supply and a power supply are issues that must be addressed by many mining projects. Mining operations may be in competition with local water users for the available clean water resources. In addition, the greenhouse gas emissions from mine site power plants are also an industry concern. If your project has both water and power supply issues and it is close to tidewater, then there might be a new solution available.
I recently attended a presentation for an oil & gas related technology that is now being introduced to the mining industry. It is an innovative approach that addresses both water and power issues at the same time.
The technology consists of a floating LNG (liquefied natural gas) turbine power plant combined with high capacity seawater desalinization capabilities. MODEC is offering the FSRWP® (Floating Storage Regasification Water-Desalination & Power-Generation) system.
MODEC also has associated systems for power only (FSR-Power®) and water only (FSR-Water®)

FSRWP capabilities

The technology is geared towards large capacity operations that have access to tidewater. It provides many tangible and intangible operational and environmental benefits.  It can:
  • Generate fresh water supply (10,000 – 600,000 m3 /day)
  • Generate electrical power (80 to 1000 MW) using LNG
  • Can provide power inland (>100 km) from a tidewater based floating power plant
  • Can provide natural gas distribution on land via on-board re-gasification systems
  • Has LNG storage capacity of 135,000 cu.m
  • Has a refueling autonomy of 20 to 150 days
  • Allows low cost marine delivery of bulk LNG supply

Procurement & Application

The equipment can be procured in several ways. For instance it can be contracted as an IPP (Independent Power Producer), purchased as an EPCI (Engineering, Procurement, Construction and Installation), BOO (Build, Own and Operate) or BOOT (Build, Own, Operate and Transfer).
Typically it takes 18-24 months of contract award to deliver to the project site, although temporary power solutions can be provided within 60-90 days.
From a green mining perspective, the FSRWP produces clean power with the highest thermal efficiency and lowest carbon foot-print.
See the table for a comparison of different power generation efficiencies and carbon emissions per kW.
Gas turbines are not new technology to MODEC.  They currently own & operate 42 such generators, which can produce roughly 43 MW (each) in combined-cycle mode.

Mooring options

Currently there are three mooring options for the floating system that should fit most any tidewater situation.
Jetty or Dolphin mooring is suitable for protected areas or near-shore applications where the water depth is in the range of 7 to 20 meters.
Tower Yoke mooring is ideal for relatively calm waters where the water depth is between 20 to 50 meters.
External Turret mooring is similar to a Tower-Yoke and is ideal for water depths exceeding 50 meters or where the seabed drops off steeply into the ocean.

Power transmission

Twenty years ago it was impractical to transmit AC power long-distances and subsea power cable technology was not as advanced as it is today. Hence an offshore power plant like a FSRWP was not technically viable. Due to R&D efforts over the last 15 years it is now possible to economically transmit AC. For example it is possible to transmit up to 100 MW over 100 miles through a single subsea cable. In addition, it is also viable to transit 200 MW at 145 kV from a vessel to shore.

Water treatment

Modern FSRWP’s use reverse osmosis membrane technology to produce industrial or potable water.  This is similar to most conventional onshore desalination plants.
The main benefits of floating offshore desalination are increased overall thermal efficiency if both power and water production are combined on a single vessel. In addition, seawater sourced offshore and rejected brine discharged offshore minimizes risk to coastal marine life.

Conclusion

The bottom line is that if your mining project is near shore, and has both water supply and power issues, take a look at the FSRWP technology. One might say it is greener technology by using LNG (rather than coal, heavy fuel oil, or diesel) to generate power.  At the same time it avoids competition with locals for access to fresh water.
This technology won’t be suitable for all mining situations, but perhaps your mine site fits the model. Reportedly rough costs for power are in the range of $0.10-$0.14/kwh with a capital cost of $1M-$1.5M per MW.
There will be minimal closure costs associated with dismantling the power plant.  One just floats it away at the end of the mine life.
Check out the MODEC website if you wish to learn more: https://www.modec.com/fps/fsrwp/index.html
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
For those interested in reading other mining blogs, check out the Feedspot website at the link below. They list 60 mining related blog sites that you check out. https://blog.feedspot.com/mining_blogs/
Share

Flawed Mining Projects – No Such Thing as Perfection

Recently I read a post on LinkedIn where somebody was asking what key metrics companies are looking for in order to develop (or provide financing to) a new mining project. It’s more than just a project having a good NPV or IRR.  They are also looking at how difficult it is to achieve the targeted NPV.
Mining companies are always on the hunt for new projects to grow their cashflows. They would all like to find the “perfect” project; one with ideal conditions and great attributes.
However those perfect projects likely don’t exist anymore, if they ever even did.
Consequently companies must be willing to accept some potential flaws (or risks) in their go-forward projects.
The question is what flaws are they willing to accept and how far away from the ideal situation are they willing to go.

What makes a perfect project?

If one could envision a perfect mining project, what might it look like?   Here are some attributes that one would want to see (in random order). If a project had 100% of these, it would be a fantastic project.
    • A high grade ore orebody
    • A large reserve and long mine life to ride out commodity price cycles
    • Low operating cost
    • Low cash cost, in the bottom quartile of costs
    • Well defined ore zones, allowing simple mining with low dilution
    • A geotechnically competent rock mass
    • Clean and straightforward metallurgy
    • Consistent and straightforward permitting regulations
    • A stable government and stable fiscal regime
    • Safe security conditions for site personnel
    • High NPV and high IRR
    • No acid runoff issues from waste products
    • Stable tailings disposal conditions
    • Readily available local workforce / local power supply / good water supply
    • Favorable local community and stakeholder support
Other readers may have more attributes that they would like to see if asked to theorize “What constitutes a perfect mining project?”

Take off the promoter hat

backhoe on soft claysNow take an honest look at some recent (or past) projects that you have been involved with. How many of the perfect attributes listed above would be represented? It would be surprising to see them all checked off. Unfortunately that means certain flaws (risks) must be accepted when developing a project.
Each company (or financier) will have their vision as to which attributes are “must have” and which ones are “nice to have”.

But we have risk tools

There are many risk tools available to help in evaluating the potential flaws in a project. Unfortunately these tools don’t make the decisions for management.
Risk based Monte Carlo analysis requires management to pre-define the magnitude of the risks and then decide upon what probability of success is acceptable. Real option analysis or decision trees or Kepner-Tregoe are examples of other tools that can help in the decision making process.
Ultimately risk is risky.  Management must make the go/no-go decision regardless of how many probabilistic histograms and tables they have generated. A 90% chance of success still means there is a 10% chance of failure. The probability of failure may be low, but it is not zero.
It would be interesting to examine recent failed projects to define the cause(s) of failure. One could then see if the cause was something that was pre-determined as a risk, either as a small risk or a large risk. Perhaps the cause was something that management felt could be mitigated or perhaps it was something viewed as highly unlikely. No doubt that successful projects also had risks, which were either mitigated or which (luckily) never occurred.

Conclusion

The bottom line is that management understandably have a difficult task in making go/no-go decisions. Financial institutions have similar dilemmas when deciding on whether or not to finance a project.
In my career I have sat in on such management discussions and it’s never been a simple process, mainly because no project is perfect. Management know all the flaws (at least they think they do) and thus have to decide whether to push forward knowing the flaws exist.
I fully expect that future mining project risk will increase due to the complexity of project designs and broadening of stakeholder dynamics. Hence decision making in the mining industry isn’t going to get any easier regardless of the decision tools being used.  Look at your own situation, are your projects getting easier or harder?
One should examine the impact of the project flaws on the project economics.  The most common way to do this is the sensitivity chart (i.e. spider graph).  However this itself is a flawed way to evaluate the flaws.  You can read why at this blog post “Mining Cashflow Sensitivity Analyses – Be Careful“.
A better approach is to use a probabalistic analysis, like Monte Carlo simulation, that can examine multiple factors at the same time.   I discuss the benefits of this approach in a blog post ” Mining Financial Modeling – Make it Better!
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
Share

Mining Due Diligence Checklist

It doesn’t matter how long you have worked in the mining industry, at some point you will probably take part in a due diligence review. You might have been asked to help create a data room. Perhaps your company is looking at a potential acquisition. Maybe you’re a consultant with a particular expertise needed by a due diligence team. It’s likely that due diligence has impacted on many of us at some point in our careers.
The scope of a due diligence can be exceptionally wide. There are legal, marketing, and environmental aspects as well as all the technical details associated with a mining project. The amount of information provided can be overwhelming.

Checklists are great

Checklists are great and can be very helpful in a due diligence review. A detailed technical scope checklist is a great way to make sure things don’t fall through the cracks. A checklist helps keep a team on the same page and clarifies individual roles and tasks. Checklists bring focus and minimize sidetracking down unnecessary paths.
Recognizing this, I have created a personal due diligence checklist for these exercises. A screen shot of it is shown below. The list is mainly tailored for an undeveloped mining project still at the study stage, but it still has over 230 items that might need to be considered.

Every mining due diligence is unique

Not all of the items in the checklist are required for each review. Maybe you’re only doing a high level study to gauge management’s interest in a project. Maybe you’re undertaking a detailed review for an actual acquisition or financing event. It’s up to you to create your own checklist and highlight which items need to be covered off. The more items added the less risk of missing something in the end.
You a create your own checklist but if you would like a copy of mine just email me at KJKLTD@rogers.com and let me know a bit about how you plan to use it (for my own curiosity). Specify if you would prefer the Excel or PDF versions.
Please let me know if you see any items missing or if you have any comments.

Due Diligence isn’t for everyone

Mining due diligence exercises can be interesting and great learning experiences, even for senior people that have seen it all. However they can also be mentally taxing due to the volumes of information that one must find, review, and comprehend, all in a short period of time.
Some people are better at due diligence than others. It helps if one has the ability to quickly develop an understanding of a project. It also helps to know what key things to look for, since many risks are common among projects.
Further on the topic of mining due diligence, I have a previous blog post triggered by my frustrations with some poorly set up data rooms.  You can read that at “Due Diligence Data Rooms – Help!”  My request is that when setting up a mining data room, please think about the people who will be using it.
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
Share

Does the Mining Industry Employ Interns?

employing interns
Over the couple of years I have been working on a side project in the tech industry.   One of the things that struck me was the hiring of interns, both paid and unpaid.
I’m now aware that interns are being hired in other industries such as legal, politics, journalism, and marketing.  However I have never come across the use of interns within the mining industry.
Intern

Why hire interns?

I was recently talking to a marketing consultant about tips on tech marketing and one of the suggestions she made was to hire an unpaid intern.  They would do much of the legwork of finding sales contacts and establishing contact with them.
My first question was why would anyone work for free?  There are  three main reasons:
  1. For school credit; as part of a course credit in college or university where an internship is part of the program requirement.
  2. For experience; it is difficult to get a real job without experience and so the internship teaches, builds  experience, and establishes a portfolio of work.
  3. Networking; building up industry connections can possibly lead to permanent work down the road.

Its the right thing to do

At first I was taken aback at the thought of asking someone to work for my company for free.  Are we that cheap?
Thinking about it further, if you are paying someone a salary the expectation is that they should be somewhat skilled at their job.  I have come to realize that the internship may actually be a win-win for both parties.

Its a win-win

The company gets a chance to learn about potential employees and also gets productive service from them.
The intern gains employment experience and learns about the realities of the business world.  Students have already paid the schools to teach them.  Now businesses can help teach them more, but at no cost.   It’s a win-win for both.
So how did our unpaid intern search go?  We posted a free ad on indeed.ca.  Within 72 hours we received over ten replies, of which only 2-3 came close to meeting the actual qualifications.  Some of the applicants had no relevant experience at all.
Possibly in today’s job market people are willing to work for free on the hope that they can get some experience, which will hopefully lead to a permanent job in the future.

Conclusion

The question is whether the mining industry can make use of interns in the areas of geology, engineering, marketing, presentation graphics, websites, etc?
There may be many students or recent grads looking for an opportunity and are willing to do whatever it takes to  advance their careers.
Even if your operating budget can’t afford the cost of hiring another person, you may still have a chance to help out someone new in the industry.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Underground Feasibility Forecasts vs Actuals

underground costing
I recently attended a CIM Management and Economics Society presentation here in Toronto discussing the differences between actual underground production versus the forecast used in the feasibility study. The presenter was Paul Tim Whillans from Vancouver Canada.
His topic is interesting and relevant to today’s mining industry.  Paul raised many thoughtful points supported by data. He gave me permission to share his information.
The abstract for his paper is inerted below.  The paper can be downloaded at this LINK and here are the presentation slides.

ABSTRACT

An underground mining study that is done in accordance with NI43-101, JORC or similar reporting code is generally assumed by the public to be representative, independent and impartial. However, it has been well documented by academics and professionals in our industry that there is a sharp difference between the forecasts presented in these underground studies and the actual costs when a mine is put into production.
For underground mines, the risks associated with obtaining representative information are much greater than for surface mining and the cost of accessing underground ore is also proportionally much greater. There is a pressing need to align expectations, by improving the accuracy of projections. This will result in reduced risk to mining companies and investors and provide more reliable information to government agencies, the public, and more importantly, the communities in which the proposed mine will operate.
The objective of this article and an article currently being written titled “Mining Dilution and Mineral Losses” is to:
– Discuss the dynamics of intention that lead to over-optimism;
– Provide simple tools to identify which studies are likely to be more closely aligned with reality;
– Identify some specific points where underground mining studies are generally weak;
– Discuss practices currently in use in our industry that lead to a composite or aggregate effect of over optimism;
– Describe the effects of overly optimistic studies;
– Outline specific changes that are necessary to overcome these challenges; and
– Stimulate discussion and awareness that will lead to better standards.”

Conclusion

I agree with many of the points raised by Paul in his study. The mining industry has some credibility issues based on recent performance and therefore understanding the causes and then repairing that credibility will be important for the future.
Credibility ultimately impacts on shareholder returns, government returns, local community benefits, and worker health and safety; so having a well designed mine will realize benefits for many parties.
If you need more information Paul’s website is at http://www.whillansminestudies.com/
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Resource Estimates – Are Independent Audits A Good Idea?

mining reserves
Question: How important is the integrity of a tailings dam to the successful operation of a mine?
Answer: Very important.
Tailings dam stability is so important that in some jurisdictions regulators may be requiring that mining companies have third party independent review boards or third party audits done on their tailings dams.  The feeling is that, although a reputable consultant may be doing the dam design, there is still a need for some outside oversight.
Differences in interpretation, experience, or errors of omission are a possibility regardless of who does the design.  Hence a second set of eyes can be beneficial.

Is the resource estimate important?

Next question is how important is the integrity of the resource and reserve estimate to the successful operation of a mine?
Answer: Very important.  The mine life, project economics, and shareholder value all rely on it.     So why aren’t a second set of eyes or third party audits very common?

NI 43-101 was the first step

In the years prior to 43-101, junior mining companies could produce their own resource estimates and disclose the results publicly.  With the advent of NI 43-101, a second set of eyes was introduced whereby an independent QP  could review the company’s internal resource and/or prepare their own estimate.  Now the QP ultimately takes legal responsible for the estimate.
Nowadays most small companies do not develop their own in-house resource estimates.  The task is generally awarded to an independent QP.

Resource estimation is a special skill

Possibly companies don’t prepare their own resource estimates due to the specialization needed in modelling and geostatistics. Maybe its due to the skills needed to operate block modeling software.   Maybe the companies feel that doing their own internal resource estimate is a waste of time since an independent QP will be doing the work anyway.

The QP is the final answer..or is it?

Currently it seems the project resource estimate is prepared solely by the QP or a team of QP’s.   In most cases this resource gets published without any other oversight. In other words no second set of eyes has taken a look at it.  We assume the QP is a qualified expert, their judgement is without question, and their work is error free.

Leapfrog Model

As we have seen, some resources estimates have been mishandled and disciplinary actions have been taken against QP’s.   The conclusion is that not all QP’s are perfect.
Just because someone meets the requirements to be a Competent Person or a Qualified Person does not automatically mean they are competent or qualified. Geological modeling is not an exact science and will be based on their personal experience.

What is good practice?

The question being asked is whether it would be good practice for companies to have a second set of eyes take a look at their resource estimates developed by independent QP’s?
Where I have been involved in due diligence for acquisitions or mergers, it is not uncommon for one side to rebuild the resource model with their own technical team.  They don’t have 100% confidence in the original resource handed over to them.   The first thing asked is for the drill hole database.
One downside to a third party review is the added cost to the owner.
Another downside is that when one consultant reviews another consultant’s work there is a tendency to have a list of concerns. Some of these may not be material, which then muddles the conclusion of the review.
On the positive side, a third party review may identify serious interpretation issues or judgement decisions that could be fatal to the resource.
If tailings dams are so important that they require a second set of eyes, why not the resource estimate?  After all, it is the foundation of it all.
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
Share

Measured vs. Indicated Resources – Do We Treat Them the Same?

measured and indicated
One of the first things we normally look at when examining a resource estimate is how much of the resource is classified as Measured or Indicated (“M+I”) compared to the Inferred tonnage.  It is important to understand the uncertainty in the estimate and how much the Inferred proportion contributes.   Having said that, I think we tend to focus less on the split between the Measured and Indicated tonnages.

Inferred resources have a role

We are all aware of the regulatory limitations imposed by Inferred resources in mining studies.  They are speculative in nature and hence cannot be used in the economic models for pre-feasibility and feasibility studies. However Inferred resource can be used for production planing in a Preliminary Economic Assessment (“PEA”).
Inferred resources are so speculative that one cannot legally add them to the Measure and Indicated tonnages in a resource statement (although that is what everyone does).   I don’t really understand the concern with a mineral resource statement if it includes a row that adds M+I tonnage with Inferred tonnes, as long as everything is transparent.
When a PEA mining schedule is developed, the three resource classifications can be combined into a single tonnage value.  However in the resource statement the M+I+I cannot be totaled.  A bit contradictory.

Are Measured resources important?

It appears to me that companies are more interested in what resource tonnage meets the M+I threshold but are not as concerned about the tonnage split between Measured and Indicated.  It seems that M+I are largely being viewed the same.  Since both Measured and Indicated resources can be used in a feasibility economic analysis, does it matter if the tonnage is 100% Measured (Proven) or 100% Indicated (Probable)?
The NI 43-101 and CIM guidelines provide definitions for Measured and Indicated resources but do not specify any different treatment like they do for the Inferred resources.
CIM Resources to Mineral Reserves

Relationship between Mineral Reserves and Mineral Resources (CIM Definition Standards).

Payback Period and Measured Resource

In my past experience with feasibility studies, some people applied a  rule-of-thumb that the majority of the tonnage mined during the payback period must consist of Measure resource (i.e. Proven reserve).
The goal was to reduce project risk by ensuring the production tonnage providing the capital recovery is based on the resource with the highest certainty.
Generally I do not see this requirement used often, although I am not aware of what everyone is doing in every study.   I realize there is a cost, and possibly a significant cost, to convert Indicated resource to Measured so there may be some hesitation in this approach. Hence it seems to be simpler for everyone to view the Measured and Indicated tonnages the same way.

Conclusion

NI 43-101 specifies how the Inferred resource can and cannot be utilized.  Is it a matter of time before the regulators start specifying how Measured and Indicated resources must be used?  There is some potential merit to this idea, however adding more regulation (and cost) to an already burdened industry would not be helpful.
Perhaps in the interest of transparency, feasibility studies should add two new rows to the bottom of the production schedule. These rows would show how the annual processing tonnages are split between Proven and Probable reserves. This enables one to can get a sense of the resource risk in the early years of the project.  Given the mining software available today, it isn’t hard to provide this additional detail.
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
Share

3D Model Printing – Who To Contact?

One of the technologies that is still getting a lot of press is 3D printing.  It seems new articles appear daily describing some fresh and novel use. Everything from home construction, food preparation, medical supplies, and industrial applications, 3D printing continues to find new applications in a wide range of disciplines.

Mining can take advantage of 3D printing

In a previous blog “3D Printing – A Simple Idea”, I discussed the helpfulness of printing 3D topographic models for the team members of a mining study. I was recently contacted by a consulting firm in Texas that specializes in printing 3D mining models. Here is their story and a few model images as provided to me by Matt Blattman of Blattman Brothers Consulting. (www.blattbros.com/3dprinting)

Blattman Brothers Consulting

Their 3D printed models are used in the same way geologists and mining engineers have employed models for decades. In the past we saw the physical models made of stacked mylar or plexi-glass maps, wood or foam core. We recognized that there is value in taking two dimensional sections or plan maps and making a 3D representation.  This provides more information than those viewed on a computer screen.
Physical models convey scale, interactions and scope in ways that no other method can. Technology like 3D printing improves the model-making process by allowing the addition of high def orthophotos, reducing the model cost, increasing its precision and delivery time.
Currently 3D models can be made in a variety of materials, but the primary three are extruded plastic, gypsum powder, or acrylics.
  • Plastic models (ABS or PLA) are cheap, fast and can created on relatively inexpensive, hobbyist printers. The downside to these models is that the number of colors available in a single model are limited, typically a single color.
  • Powder-based printers can typically print in 6.5M colors, allowing for vibrant, photo-realistic colors and infinite choices for title blocks, logos and artistic techniques. However, gypsum models can be as fragile as porcelain and require some care in handling.
  • Acrylic models allow for translucent printing (“looking into the ground to see the geological structure”) and are more durable than the gypsum. Nevertheless, acrylic models are significantly more expensive than the other two types and the color palettes are limited.
Here are some examples.
Leapfrog Model

Leapfrog Model

Geological Model in Acrylic

Acrylic Model

Powder Based 3D Model

Powder Based 3D Model

Powder Based 3D Model

Powder Based 3D Model

Besides having another toy on your desk beside your stress ball, why not print off your mine plan, or print the geology shapes and topography? It’s all about communicating highly technical data to a non-technical audience, whether that audience is a permitting authority, the general public, or maybe even company management.
The ability to grasp a map or technical drawing is a learned skill and not everyone has it. If you’ve just spent $20M on a feasibility study, why assume that the attendees in a public meeting will fully appreciate the scale and overall impact of your proposed project with 2D maps?
That message can be better conveyed with a model that is easily understood. One of Blattman’s clients, Luck Stone, recently described how they use their 3D printed models in this video.

Blattman’s models are created from the same 3D digital data already in use by most companies involved in geological modeling and mine design. Other than the units (meters versus millimeters), the triangulated surfaces created by the software are no different than those created by mechanical or artistic 3D modeling programs.
While many 3D printing services are available on the market, not all of them are able to speak “mining”. They may not be able to walk the skilled geologist or mining engineer through the process of creating the necessary digital formats and that’s where Blattman comes in. With more than 20 years of mining experience and having already gone through the 3D printing learning curve, they can assist any natural resource company through the process, either as a full-service/turn-key project or just to advise the client on how to prepare their own files.

Conclusion

The bottom line is that 3D printing is here to stay and its getting better each year.   Go ahead and check out the technology to see if it can advance your path forward .
We would be interested in hearing about any experiences your have had with 3D modelling, pro’s and con’s.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.
Share

Constraints: Use Them to Your Advantage

mining study management
I recently read a business book called “A Beautiful Constraint: How to Transform Your Limitations into Advantages, and Why It’s Everyone’s Business” by Adam Morgan and Mark Barden. It describes how to use constraints, like lack of time, or money, or resources and use them to help transform your company for the better.
Here’s an Amazon link to the book.  Beautiful Constraint Book Cover
The book discusses how to shift away from the typical “victim” role by understanding how our routines control things, ask the right questions, and focus on “how” and not “if”.

Focus on HOW and not IF

A good example: one of the recommendations in the book is in your team meetings no one on your team is allowed to utter the words “we can’t because…”.  They must replace those words with “we can if…”.   This forces the generation of ideas and promotes a positive attitude rather than a victim attitude.
The book describes how many innovative ideas are due to constraints and those innovations would never have come about without those constraints.
To force innovation in your organization you can create artificial constraints for your team.  This will foster innovative thinking and push for “outside the box” ideas.  The tougher the constraint, the greater the challenge for your team.  Possibly the greater the final outcome too.
The term Theory of Constraints may be common to some.  However that concept is different than what is being discussed in the book.  The TOC essentially relies on managing a constraint or eliminating it, and then addressing the next constraint in sequence.
The book authors instead propose to exploit the constraint or leverage it to create a new possibility.  Hence the title “beautiful constraint”.

Mining has no shortage of constraints

We all know the mining industry has more than enough constraints placed upon it today. It may be lack of funding, lack of skilled talent, environmental pressures, supply-demand issues, social issues, or security issues.  Each mining project may have additional constraints, so one probably doesn’t need to create artificial constraints for the team.
The mining industry has no option but to try to use these constraints in a constructive manner.  Miners must not let them pull the industry down nor simply wait until they go away.  When people say “Mining is cyclical and it will all turn around soon.”, that’s an example of waiting for the constraint to go away.

How long do you wait before taking your own action?

The bottom line is that the book is an eye opener and enlightening.  It may be telling some of us what we already know deep inside but don’t acknowledge openly.  Don’t wait any longer, start innovating, and don’t be afraid of grand innovations.
Note: If you would like to get notified when new blogs are posted, then sign up on the KJK mailing list on the website.  Otherwise I post notices on LinkedIn, so follow me at: https://www.linkedin.com/in/kenkuchling/.
Share

Meetups and Mining Millennials

mining millenials
Over the last year I have had many encounters with the Toronto tech start-up community.  I have noticed some similarities with the junior mining industry but some differences also.
The tech start-up model is similar to the junior mining business model as it relates to early stage funding followed by additional financing rounds.  One obvious difference is that mining mainly uses the public financing route (IPO’s) while the tech industry relies on private equity venture capital (VC’s).
There are also some less obvious differences.
Generally the tech industry is young, vibrant, technology-savvy, and applies the latest in social technology to collaborate.  The mining industry seems to be lagging behind on many of these aspects.
The following article will describe a few of my observations. As you read through this, ask yourself “Should the mining industry be doing these things?”

Tech Meetups and Networking

My first experience with the tech industry was associated with the many after-hours networking meetings called “meetups”.  They are held weeknights from 6 to 9 pm  and consist of guest speakers, expert panels, and for general networking purposes.   Often guest speakers will describe their learnings in starting new companies and failures they had along the way.
The meetups may also provide “how-to” advice for techniques like Google Analytics, Facebook advertising, Google Adwords, email marketing, etc.).
Attending these meetups is usually free.  They are typically held after hours at different tech company offices and they often provide free beer and pizza. One can see the entire industry working together for the betterment of the industry.

How to Organize Meetups

Scheduling of meetups is done via the online software platforms Meetup or eventbrite.  Both of  these work well for announcing the meeting notice and tracking signups and attendees.
By the way, meetups are not only tech-related; they are also held for interest groups for hiking, theatre, writing, yoga, business marketing, etc.  The platforms provide a good way to manage communities.  Unfortunately here in Toronto there are no geology or mining related meetups so the mining industry may be missing out on a good way to build a more collaborative community.
The mining industry does have some local meetings, as far as I know there are mainly three after-hour mining events.  The CIM has a monthly luncheon with a cost of $50-$65 (not exactly inclusive to everybody).   There is a Toronto Geological Discussion Group that holds monthly meetings and seems to be comprised of the older geologist demographic.  The third event is Mining 4 Beer, which a small group that meets intermittently at a local bar.  These few events limit the amount of buzz for those working in the mining industry.  There are a lot of mining companies here with a lot of mining people but not a lot of vibrancy.

Where to hold an event

Most of the tech meetups are held in local tech offices.  These offices are great. They have an open concept, pool tables, ping pong, video games, fully stocked kitchen. Who wouldn’t want to work there?
The last time I was in the offices of a large engineering firm I felt like a lab rat in a cubical maze.   I’m not saying engineering offices can switch to a tech office layout, but more enjoyment of the office environment might help draw more people to the mining industry.
Perhaps it’s easier to have a positive work attitude when money is being thrown at you (as is happening in the tech world) rather than having to scratch and claw for funds like mining must do right now.   However I suggest if one wants more smart young people to come into the industry then one needs to adapt.  This means more than just buying the latest 3D geological software.  It means creating an environment that people want to work in.
In the late 1990’s I was working in the Diavik  engineering office in Calgary.  They provided a unique office layout whereby everyone had an “office” but no front wall on the office so you couldn’t shut yourself in.  There were numerous map layout tables scattered throughout the office to purposely foster discussion among the team.
A similar type philosophy is used by Apple in their office layout design where even the kitchen placement has a purpose.  People should mingle and run into one another to promote conversation.  Discussion is good. Camping out in an office is not good.

Keep it short and to the point

Another thing I noticed with the tech industry is that when start-up tech companies are given an opportunity to tell their story, typically they only have 5 to 10 minutes to pitch.  No long winded thirty page PowerPoint presentation to explain what they are doing.
The tech industry is also big on the “elevator pitch”, a one minute verbal summary of what they are doing.  The tech people are taught to be concise.  If you can’t explain it in plain language in one minute then it’s too complicated.
For comparison, many mining investor presentations can be long, highly technical, and tailored to other technical people and not the average person.   One must ask who is the real target audience for those presentations?

Communication methods

The tech industry relies a lot on remote workers.   They might be overseas or spread around Canada. For communication and collaboration, they use various online systems such as Slack, Google Hangout, Trello.  No more  long email threads with five people cc’d on each email.   Slack uses a chatting approach, similar to text messaging, which makes it easier to follow the conversation and share files.
Can the mining industry be taught to use something new like Slack?  I don’t see a problem with that as long as one honestly wants to learn it. It’s really not that complicated.
For interest, another blog provides some more discussion on online collaboration software “Online Collaboration and Management Tools“.

Conclusion

The bottom line is that I can see a great difference in the attitude and atmosphere in the tech industry compared to the mining industry.  The junior mining game was the precursor for the tech start-up industry but has not kept pace with evolving work techniques.
As senior personnel retire from mining, the loss of this mining experience will be felt.  However the new ideas that may follow could be a positive outcome.
Share