Articles tagged with: Mine Engineering

The Anatomy of 43-101 Chapter 16 – Mining (Part 2)

Part 2 of this blog post will focus on the remaining engineering work to finish Chapter 16 of the Technical Report. We only wrote about half of it in Part 1. The mining engineer can generally handle the rest of these tasks without requiring a lot of external input. You can read Part 1 at this link “The Anatomy of 43-101 Chapter 16 – Mining (Part 1)”.
The pit design and phases were completed at the end of Part 1, and we can move on to scheduling.

4. Production Scheduling

Once the pit design is complete, everyone will be calling for the production schedule as soon as possible. Others on the team are waiting for it. The tailings engineers need the production schedule for the tailings stage design. The process engineers need the scheduled head grades to finalize sizing the plant components. The client wants the schedule to plug into their internal cashflow model for a quick peek at the economics.
However, before the mine engineer can start scheduling, the dilution approach needs to be selected. Dilution is waste that is mixed in with ore during mining. A high amount of dilution can dramatically lower the processed head grades. There may be a desire to “low ball” the dilution to make the grades look better, but the engineer should base the dilution on what they would expect to see.
Two dilution approaches are common. One can either construct a diluted block model; or one can apply dilution afterwards in the production schedule. I have used both approaches at different times.
The production schedule must be on a diluted basis, since that represents what the processing plant will actually see.
Generally, two different production schedules must be created: (i) a Mining schedule, and (ii) a Processing schedule. In some instances, they may be one and the same schedule. However, if any ore stockpiling is done, then the Mining schedule will be separate from the Processing schedule.
The Mining schedule shows ore going directly to the plant and ore going into the stockpiles. The Processing schedule will show ore delivered directly from the mine and ore reclaimed from stockpiles. Building stockpiles and pulling ore from stockpiles are two independent activities.
ore stockpileSometimes lower grade stockpiles are built up by the mine each year but only processed at the end of the mine life. Periodically the ore mining rate may exceed the processing rate and other times it may be less.  This is where the stockpile provides its service, smoothing the ore delivery to the plant.
Scheduling can be done with variable time periods. Perhaps the schedule is generated using monthly time periods, or quarters, or years.
The 43-101 report will normally show the annual production schedule, but that does not mean it was generated that way. I prefer to use short time periods (monthly or quarterly) for the entire mine life, to ensure ore is always available to feed the plant. A 10 year mine life would result in 120 monthly time periods, so output spreadsheets can get large.
Scheduling can be done manually (in Excel) or by using commercial software, like Datamine’s NPVS. The commercial software is better in that it allows one to run different scenarios more quickly, and it does a lot of the thinking for the engineer. It also does a good job of stockpile tracking. It also decides when it is necessary to transition to mining in satellite pits.
Once the schedules are finalized, they are normally reviewed by the client for approval. The strip ratio and ore grade profile by date are of interest. One may then be asked to look to at different stockpiling approaches to see if an NPV (i.e. head grade) improvement is possible.
One can stockpile lower grade ore and feed the plant with better grade by mining at a higher rate with more equipment. One might need to examine iterative schedules of that type.
Sometimes one must take two steps backwards and re-design some of the initial pit phases to reduce waste stripping or improve grades. Then one would run the schedules again until getting one that satisfies everyone.
Now that the schedule is complete, we can write up the Chapter 16 text up to page 15. We’re getting closer to the end.

5. Site Layout Design

Diavik mines

With the pit tonnages and mining sequence from the schedule, the mine engineers can start to look at the site layout (waste dumps and haul roads). Normally the tailings engineers will be responsible for the tailings layout. However, if there is no tailings engineer on the PEA team, the mining engineer may look after this too.
First there is a need for a waste balance. This defines how much mined overburden or waste rock will be needed to build haulroads, laydown pads, and tailings dams. Then the remaining waste volume must be placed into waste dumps.
Hopefully the tailings engineers have finished their tailings dam construction sequence by this time to provide their rockfill needs (although unlikely if you only gave them the production schedule two days ago).
The geotechnical engineers will provide the waste dump design criteria; for example, 3:1 overall side slope using 15m high dump lifts. Ideally it is nice to have soil and foundation information beneath the waste dump sites, but at PEA stage most often this isn’t available. The dump locations are only being defined now.
The mining engineers will size the various waste dumps to their required capacity. Then they can lay out the mine haulroads from the pit ramps exits to the ore crusher, the ore stockpiles, and to each waste dump.
That’s it for the site layout input. Add another 2 pages to Chapter 16. Now the mining engineers can look at the mining equipment fleet.

6. Fleet Sizing and Mining Manpower

The last task for the mine engineer in Chapter 16 is estimating the open pit equipment fleet and manpower needs. The capital and operating costs for the mining operation will also be calculated as part of this work, but the costs are only presented in Chapter 21.
The primary pieces of equipment are the haul trucks. They can range in size from 30 tonnes to 350 tonnes and anywhere in between.
Typically, the larger the equipment is, the lower the unit cost ($/t), especially in jurisdictions where labor costs are high. One doesn’t want a mine fleet with only 5 trucks nor one with 50 trucks. So where is the happy medium?
Once the schedule and site layout are complete, the mine engineers can run the truck haul cycles, in minutes. They need to estimate the time to drive from the pit face, up the ramp, to the waste dump, to the ore crusher, and return back into the mine. Cycle times determine the truck productivity, in tonnes per hour per truck and include the time to load the truck. Some destinations may have long cycle times (to a far off crusher) while others may be quick (to an adjacent waste dump).

Open Pit Slope

The cycle time must be calculated for each material type going to each destination. As the pit deepens, the cycle times increase.
Very simplistically, if a 100 tonne truck has a 20 minute cycle time, it can do three cycles in an hour (300 tph). If one has to mine 10 million tonnes of ore per year, then that would require 33,300 truck hours. If a single truck provides 6500 operating hours per year, that activity would require a fleet of 5 trucks. The same calculation goes for waste.
The total trucking hours will vary year to year as waste stripping tonnages change or haul cycle times increase in deeper pits. The required truck fleet may vary year to year.  Keeping haul distance short and haul cycles quick is the key to a lower cost mine.
The mine engineers undertake the productivity calculations for loading equipment to estimate annual operating hours, and the required shovel / loader fleet size.
The support equipment needs (dozers, graders, pickups, mechanics trucks, etc.) are typically fixed. For example, 2 graders per year regardless if the annual tonnages mined fluctuate.
The support equipment needs are normally based on the mining engineer’s experience. Hence the benefit of actually working at a mine at some point in your career.
Blasting includes both the blasthole drilling activity and hole charging. The mining engineer estimates drill productivity and specifications based on the bench height, the expected rock mass quality, and the power factor (kg/t) need to properly demolish the rock.
Finally, the mine operation manpower is estimated based on all the equipment operating hours as well as the fixed number of personnel to support and supervise the mine.
This essentially concludes the mining information presented in Chapter 16 of a typical 43-101 open pit report.

Conclusion

These two blog posts hopefully give an overview of some of the things that mining engineers do as part of their jobs. Hopefully the posts also shed light on the amount of work that goes into Chapter 16 of a 43-101 report. While that chapter may not seem that long compared to some of the others, a lot of the effort is behind the scenes.
Some will say PEA’s are not very accurate documents that should be taken with a grain of salt. One should understand that engineers are working with a limited amount of information at this early stage while forming the concept for the proposed operation.
The subsequent study stages are where more accurate costs are expected and can be demanded.
I don’t know if this overview makes one want to sign up to be a mining engineer or learn to code instead. None of this is rocket science; it just requires practical thinking.
If young people want to get into mining, but not sure into which aspect, I suggest go read through a 43-101 report. There are sections describing exploration, resource modelling, mine engineering, metallurgy, geotechnical engineering, environmental, and financial modelling. Its all in one document. See if any of these areas are of interest to you. Universities should use 43-101 reports as part of their mining engineering curriculum.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

The Anatomy of 43-101 Chapter 16 – Mining (Part 1)

When people learn that I’m a mining engineer, I’ll normally get perplexed looks and asked what that job is about.    Most never even knew the job existed.
So I thought what better way to explain the mining engineer role than by describing the anatomy of a typical Chapter 16 (MINING) in a 43-101 Technical Report.  That chapter is a good example of the range of tasks typically undertaken by mining engineers.
Secondarily it also provides an opportunity to describe in detail all the steps that go into writing a Chapter 16, focusing on the PEA.
PEA’s tend to have a poor reputation for lack of accuracy, and this blog post may shed some light on why that is.  To avoid running on too long, I have subdivided this into Part 1 and Part 2.
Generally, one will see a single QP sign off on Chapter 16.  However, the chapter requires input from several people.   Section 16 is generally prepared in the same way for a PEA or a feasibility study (FS).   The main difference is related to the amount of hard supporting data in a FS versus a PEA.
The PEA will rely on many “reasonable assumptions” and it can be done in at least half the time of a FS.  A FS will also build on previous study decisions, something a PEA doesn’t have access to since it is a first time snapshot of a project.
Normally preparing Chapter 16 is done under time pressure to deliver results as quickly as possible.  Other study team members are waiting for its output to finalize their own engineering work.

1. Define the Mine

In a PEA, the first thing that must be conceptualized is whether this will be an open pit (OP) mine, underground (UG), or a combination of both.
Geological pit sectionThere is always a mineral resource estimate available before doing a PEA.   The way the resource is reported will indicate what type of mine this likely is.  The geologists have already done some of the mining engineer’s work.
The mineral resource will suggest if this will be an OP or UG, a large or small operation, a long life or short life, and the likely processing method. The framework for the project is already set at the mineral resource estimate stage.
We can now write page 1 of Chapter 16.

2. Optimize the Pit Size and Shape

The first step for the mining engineer is a pit optimization analysis to define the approximate size and shape of the pit.  The pit optimization step creates a series of nested economic pit shells for different metal prices.  For example, the base case gold price may be $1800/oz, but we still want to see what size of pit would be economic at $1000/oz, $1200, $1300, etc.   Normally one may run 50 different price scenario increments.   The smaller shells may eventually be good starter pits to help improve NPV and payback time.
Before starting pit optimization, we require economic inputs from several people.   The base case metal prices must be selected (normally with input from the client).  The mining operating cost per tonne must be estimated (by the mining engineer).  The processing engineers will provide the processing cost and recovery for each ore type.
The geotechnical engineers will provide approximate pit wall angles.  All  of these inputs have to be forecasted at a very early stage.  We don’t yet know the size of the pit, the ore tonnage available, nor the actual plant throughput rate but one must still predict some costs.  Hence these initial inputs might just be ballpark data.
In the final cashflow model you may eventually see slightly different metal prices, costs, or recoveries than used in pit optimization.  That’s because that cashflow model inputs are generated by the study, while the optimization inputs are pre-study estimates.
The pit optimization step may also need to apply constraint boundaries.  For example, if there is a nearby property limit or river, one may want to constrain the pit optimization to get no closer than 50 metres to the river or boundary.   The pit shell optimizer may be free to expand the pit outwards in multiple directions, except that one direction.
Once the optimization is run, a series of nested pit shells are created, each with its own tonnes and grade.   These shells are compared for incremental strip ratio, incremental head grade, total tonnes, and contained metal.
A decision must now be made on which shell to use for the mine design.    Larger economic shells may have more tonnes, lower grade, and higher strip ratio.  Smaller shells may have lower strip ratio and better grade.
For example, a smaller shell may have 10 year life containing 800,000 oz at a strip ratio of 2:1 while a larger shell may have 14 years, 1 million oz at a strip ratio of 3:1.  Both are roughly the same economically.  However, developing the larger shell may require more mining equipment capital yet have a lower average cost per tonne. Which shell do you choose?
There can be dozens of such shell to shell trade-offs and typically one doesn’t run schedules and cost models on all of them. The client will have input on whether they wish to move forward with 10 years 800,000 oz or the 14 years with 1 million oz.  Sometimes selection is driven by investors having size expectations that need to be met.
Some people may say ‘Well… just run cashflow models for each case to see which is best”. The problem with doing too much analysis at this stage is that if you re-do the pit optimization with different recovery, operating costs, pit wall angles, you will get a different optimization result.  It becomes a question of how much detail work to do on something that is based on very preliminary input parameters.
Assuming the mining engineers have now selected the preferred shell for mine design, they can move on to mine design.  We can now write more of Chapter 16 to page 5.

3. Open Pit Design.

The mining engineer is now ready to undertake the pit design. The pit design step introduces a benched slope profile, smooths out the pit shape, and adds haulroads.   Hence a couple of key input parameters are required at this time.  The mining engineer will need to know the geotechnical pit slope criteria and the truck size & haul road widths.  Let’s look at both of these.
Pit Slopes: Geotechnical engineers are responsible for providing the slope angle criteria to the mining engineers.   The geotech engineers may have a lot or little information to work with.   Perhaps they have geotechnical oriented core holes and they have undertaken some rock strength testing.
Perhaps the only information for the geotechnical engineers is rock quality data from exploration drilling.   I have seen both situations at the PEA stage; the latter is more typical.  In the feasibility study they would have geotechnical core hole data available.  At the PEA stage, that is less likely, since no one yet knows the size and depth of the pit.  We are only getting to that now.
Pit wall schematic

Pit wall schematic

The geotechnical engineers will provide the inter-ramp slope angles, specified by catch bench widths and bench face angles.   The engineers may subdivide slopes by rock type.
For example: the overburden wall is to be at 30 degrees, the underlying oxide rock at 40 degrees and the deeper fresh rock wall at 55 degrees.  Additionally, the pit may be subdivided into pie shaped sectors, with differing slope criteria.
For example, the fresh rock on the west wall might have a 55 degree angle, but the east wall fresh rock may only allow 50 degrees and the south wall is 45 deg.
The more sectors and differing slope criteria, the more complex it is to do the pit design.   Normally you don’t see geotechnical engineers signing off as QP’s for Chapter 16, although they had key input into the pit design.
Ramps: Next the mining engineer needs to select the truck size, even though the production schedule has not yet been created.
Trucks sizes can vary between 30t up to 350t.  A double lane ramp width is approximately 4.5 times the truck width, including space for a ditch and an outer safety berm.   A 90 tonne truck is 6.7 metres wide (haulroad of 30m) while a 350 tonne truck is 9.8 m wide (haulroad of 44 m wide).    That’s a 14m width difference.
The haul road gradient is normally 10%, which means a 200 metre deep pit requires a ramp length of 2000 metres to get to the bottom.  It can be difficult to fit a 2 kilometre ramp in a small pit without pushing the walls out to provide enough circumference to get to depth.
Ramps can spiral around the pit, or they can zigzag back and forth on one side of the pit (switchbacks).  The mine engineer will decide this once they see the topography, pit size, and ore body orientation.   Adding ramps in a pit design pushes the crest outwards and adds waste to be stripped.
Pit Phases: After the pit design is complete, the mine engineer will design multiple interior phases to distribute the waste and ore tonnages in the mining schedule.  These phases are sometimes referred to as pushbacks, laybacks, or stages. At mine start-up, one doesn’t want to strip the entire top off of a large pit.   A smaller pit within the large pit will allow faster access to ore.
This completes the open pit design and now allows one to write to page 10 of Chapter 16.  However, the mining engineer is not done yet.

Conclusion

This ends Part 1.  In Part 2 we will discuss the mining engineer’s next tasks; production scheduling; waste dump design; and equipment selection.   The mining engineer QP will sign off and take responsibility for all the mine design work done so far.    You can read Part 2 at this link “The Anatomy of 43-101 Chapter 16 – Mining (Part 2)“.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.   The entire blog post library can be found at https://kuchling.com/library/
Share

Don’t Cut Corners, Cut Cross-Sections Instead

Exploration cross-sectionThis article is about the benefit of preparing (cutting) more geological cross-sections and the value they bring.
Geological sections are one of the easiest ways to explain the character of an orebody. They have an inherent simplicity yet provide more information than any other mining related graphic.
Some sections can be simple cartoon-like images while others can be technically complicated, presenting detailed geological data.
Cartoon-stylized sections are typically used to describe the general nature of the orebody. The detailed sections can present technical data such as drill hole traces, color coded assays intervals, ore block grades, ore zone interpretations, mineral classifications, etc.
Sections provide a level of clarity to everyone, including to those new to the mining industry as well as those with decades of experience.
This article briefly describes what story I (as an engineer) am looking for in sections. Geologists may have a different view on what they conclude when reviewing geological sections.
I will describe the three types of geological sections that one can cut and what each may be describing. The three types are: (1) longitudinal (long) sections; (2) cross-sections; (3) bench (level) plans. Each plays a different role in helping to understand the orebody and mining environment.
There is also another way to share simple geological images via3D PDF files. I will provide an example later.

Longitudinal (Long) Sections

Geological long section examplesLong sections are aligned along the long axis of the deposit. They can be vertically oriented, although sometimes they may be tilted to follow the dip angle of an ore zone.
Long sections are typically shown for narrow structure style deposits (e.g. gold veins) and are typically less relevant for bulk deposits (e.g. porphyry).
The information garnered from long sections includes:
  • The lateral extent of the mineralized structure, which can be in hundred of metres or even kilometers. This provides a sense for how large the entire system is. Sometimes these sections may show geophysics, drilling to defend the basis for the regional interpretation.
  • Long sections will often highlight the drill hole pierce points to illustrate how well the mineralized zone is drilled off. Is the ore zone defined with a good drill density or are there only widely spaced holes? As well, long sections can show how deep ore zone has been defined by drilling. On some projects, a few widely spaced deep holes, although insufficient for resource estimation purposes, may confirm that the ore zone extends to great depth. This bodes well for potential development in that a long life deposit may exist.
  • Sometimes the long section drill intercept pierce points can be contoured on grade, thickness, or grade-thickness. This information provides a sense for the uniformity (or variability) of the ore zone. It also shows the elevations of the higher grade zones, if the deposit is more likely an open pit mine, an underground mine, or a combination of both.

Cross-Sections

Geological pit sectionCross-sections are generally the most popular geological sections seen in presentations. These are vertical slices aligned perpendicular to the strike of the orebody. They can show the ore zone interpretation, drill holes traces, assays, rock types, and/or color-coded resource block grades.
As an engineer, my greatest interest is in seeing the resource blocks, color coded by grade. Sometimes open pit shells may be included on the section to define the potential mining volume. The engineering information garnered from block model cross-sections includes:
  • Where are the higher-grade areas located; at depth or near surface?
  • If a pit shell profile is included, what will the relative strip ratio look like? Are the ore zones relatively narrow compared to the size of the pit?
  • How will the topography impact on the pit shape? In mountainous terrain, will a push-back on pit wall result in the need to climb up a hillside and create a very high pit slope? This can result in high stripping ratios or difficult mining conditions.
  • Does the ore zone extend deeper and if one wants to push the pit a bit deeper, is there a high incremental strip ratio to do this? Does one need to strip a lot of waste to gain a bit more ore?
  • Are the widths of the mineable ore zones narrow or wide, or are there multiple ore zones separated by internal waste zones? This may indicate if lower-cost bulk mining is possible, or if higher cost selective mining is required to minimize waste dilution.
  • How difficult will it be to maintain grade control? For example, narrow veins being mined using a 10 metre bench height and 7 metre blast pattern will have difficulty in defining the ore /waste contacts.
  • Cross-sections that show the ore blocks color coded by classification (Measured, Indicated, Inferred), illustrate where the less reliable (Inferred) resources are located and how much relative tonnage may be in the more certain Measured and Indicated categories.
Geological cross-section exampleWhen looking at cross-sections, it is always important to look at multiple cross-sections across the orebody. Too often in reports one may be presented with the widest and juiciest ore zone, as if that was typical for the entire orebody.  It likely is not typical.
Stepping away from that one section to look at others is important. Possibly the character of the ore zones changes and hence its important to cut multiple sections along the orebody.

Bench (Level) Plans

Mining Bench PlansBench plans (or level plans) are horizontal slices across the ore body at various elevations. In these sections one is looking down on the orebody from above.
Level plans are typically less common to see in presentations, although they are very useful. The level plans may show geological detail, rock types, ore zone interpretations, ore block grades, and underground workings.
The bench plan represents what the open pit mining crews would see as they are working along a bench in the pit. The information garnered from bench plans that include the block model grades includes:
  • Where are the higher-grade areas found on a level? Are these higher grade areas continuous or do they consist of higher grade pockets scattered amongst lower grade blocks?
  • Do the ore zones swell or pinch out on a bench? A vertical cross-section may give a false sense the ore zones are uniform. The bench plan gives an indication on how complicated mining, grade control, and dilution control might be for operators.
  • Do the ore zones on a bench level extend out beyond the pit walls and is there potential to expand the pit to capture that ore?
  • On a given bench what will the strip ratio be? Are the ore zones small compared to the total area of the bench?
As recommended with cross-sections, when looking at bench plans, one should try to look at multiple elevations.  The mineability of the ore zones may change as one moves vertically upwards or downwards through a deposit.

Never mind cross-sections – give me 3D

While geological sections are great, another way to present the orebody is with 3D PDF files to allow users to view the deposit in three-dimensions. Web platforms like VRIFY are great, but I have been told they sometimes can be slow to use.
Mining 3D PDF file3D PDF files can be created by some of the geological software packages. They can export specific data of interest; for example topography, ore zone wireframes, underground workings, and block model information. These 3D files allows anyone to rotate an image, zoom in as needed and turn layers off and on.
You can also create your own simplistic cross-sections through the pdf menus (see image).
A simple example of such a 3D PDF file can be downloaded at this link (3D DPF File Example). It only includes two pit designs and some ore blocks to keep it simple.
The nice thing about these PDF files is that one doesn’t need a standalone viewer program (e.g. Leapfrog viewer) to view them. They are also not huge in size. As far as I know 3D PDF files only work with Adobe Reader, which most everyone already has.  It would be good if companies made such 3D PDF files downloadable along with their corporate PowerPoint presentations.

Conclusion

Exploration cross-section exampleThe different types of geological sections all provide useful information. Don’t focus only on cross-sections, and don’t focus only on one typical section.  Create more sections at different orientations to help everyone understand better.
In 2019 I wrote an article describing the lack of geological cross-sections in many 43-101 technical reports. The link to that article is her “43-101 Reports – What Sections Are Missing?
Geological sections are some of the first items I look for in a report. Sometimes they can be hidden away in the appendices at the back of the report. If they are available, take the time to actually study them since they can explain more than you realize.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Grade-Tonnage Curves – Worthy of a Good Look

Most of us have seen the typical “grade-tonnage” table or graph, showing ore tonnes and grade at varying cutoff grades. It is usually part of every 43-101 technical report in Section 14.  We may glance at it quickly and then move on to more exciting chapters. Section 14 (Mineral Resources) can be a very complex chapter to read with statistics, geostatistics, and mathematical formulae.  However the grade-tonnage curve aspect isn’t complicated at all.
The next time you see the grade-tonnage relationship, I suggest taking a few seconds to study it a bit further.   There might be some interesting things in there.

Typical Grade-Tonnage Information

Typically, one will see grade-tonnage data in 43-101 Technical Reports towards the back of Section 14 "Mineral Resources".  The information is normally presented in either of two ways; (i) a grade-tonnage table or (ii) a grade tonnage graph.  Examples of each are shown below.  The grade tonnage graph typically has the cutoff grade along the bottom x-axis and the two separate y-axes  representing the ore tonnes above cutoff and the average ore grade above cutoff.
typical grade tonnage table
typical grade tonnage curve
Rarely do you see both the table and curve in the report, although ideally one would want to see both.  Given the option, I would prefer to see the graph more than the table of numbers.  The trend of the grade-tonnage information is just as important as the values, maybe even a bit more important.  Unfortunately, a data table by itself doesn’t illustrate trends very well.

Useful Grade-Tonnage Curve Information

mining grade tonnage curveWhen I am undertaking a due diligence review or working on a study, very early on I like to have a look at the grade-tonnage information.  This could be for the entire deposit resource, within a resource constraining shell, or in the pit design.
The grade-tonnage information gives an understanding of how future economics or technical issues may impact on the mineable tonnage.
An example of a typical grade-tonnage curve is shown here.
The cutoff grade along the x-axis will be impacted by changes in metal price or operating cost. The cutoff grade will increase if metal prices decrease or if operating costs increase.
The question is how sensitive is the mineable tonnage to these economic factors. The slope of the tonnage and grade curves will help answer this question.
In the example shown, the tonnage curve (blue dots) is fairly linear, meaning the ore tonnage steadily decreases with increasing cut-off grade.  That is expected and is reasonable.
mining grade-tonnage curveHowever, if the tonnage curve profile resembled the light blue line in this image, with a concave shape, the ore tonnage is decreasing rapidly with increasing cutoff grade.   This is generally not a favorable situation.
It indicates that a significant portion of the tonnage has a grade close to the cutoff grade.  If that’s the situation, the calculation of the cutoff and the inputs used to generate it are important and worthy of scrutiny.  Are they reasonable?  Over the long term, is the cutoff grade more likely to increase or decrease?
The same logic can be used with the ore grade curve in the graph.  As  shown in this example, the ore grade increases steadily as the cutoff is raised.  This is because lower grade ore is being shifted from ore to waste, and hence the remaining ore has better quality.  If the cutoff is raised from 0.4 g/t to 0.5 g/t, then some material with a grade of about 0.45 g/t is moved from ore to waste.
I also like to compare the ratio of the average grade to the cutoff grade.  Its nice to see a ratio of 4:1 to 5:1 to ensure the overall average grade isn’t close to the cutoff.  In this example, the cutoff grade is 0.5 g/t and the average grade is 4.5 g/t, a ratio of 9:1.
The tonnage curve and grade curve provide information on the nature of the mineral resource. Study them both.

Reporting Waste Within a Shell

One complaint I have about reporting mineral resources inside a resource constraining shell is the lack of strip ratio information. This applies whether disclosing a single mineral resource estimate or variable grade-tonnage data.
In my view, the strip ratio is even more important to be aware of when looking at grade tonnage data.
The strip ratio within a shell will climb as an increasing cutoff grade results in a decreasing ore tonnage.  Sometimes the strip ratio will increase exponentially. The corresponding amount of waste remaining in that pit shell increases, hence the ratio of the two (i.e. strip ratio) can escalate rapidly.
mining strip ratio curveRegarding mineral resources, one should be required to disclose the waste tonnage and strip ratio when reporting resources inside a constraining shell. The constraining shell and cutoff grade are both based on defined economic factors such as unit mining costs, processing cost, process recoveries, and metal prices.  With respect to the mining cost component, the strip ratio is a key aspect of the total mining cost, yet it normally isn’t disclosed.
Its common to see mention that the mining cost is (say) $2.50/t, but if the strip ratio is 10:1, that equates to an effective mining cost of $27.50 per tonne of ore.   That’s an important cost to know, especially if one is pushing a pit shell deep to maximum the mineral resource tonnage.
Each mineral deposit resource model can behave differently.  Hence, in my view, the waste tonnage should be included when reporting mineral resource tonnages (or presenting grade-tonnage data) within a constraining shell.  This waste tonnage or strip ratio can be in the footnotes to the mineral resource summary table.

Spider Diagram Downsides

In 43-101 technical reports, the financial Chapter 22 normally presents the project sensitivities expressed in a spider diagram or a table format.
In a previous blog post I had discussed the flaws in the spider diagram approach.  That article link is at “Cashflow Sensitivity Analyses – Be Careful”.  The grade-tonnage curve helps explain why that is.
In the spider diagrams, we typically see sensitivities related to +/- 20% on metal prices and operating costs.    If either of these factors change, then in reality the cutoff grade would change.
If the metal price decreases by -20%, or the operating cost climbs by +20%, the cutoff grade must increase.  This adjustment is normally not made in the sensitivity analysis because it requires a lot of re-work.
Elevating the cutoff grade would shift the pit ore tonnage towards the right on the grade-tonnage curve, showing a decrease in mineable tonnes.   However, in the spider diagram logic, the assumption is that production schedule in the cashflow model is unchanged and simply the metal prices or operating costs are adjusted.  Therefore, the spider diagram can be a misleading representation of the downside risk, showing a more positive situation than in reality.

Conclusion

The grade-tonnage information is always presented in technical reports. It examines the sensitivity of the orebody size to changes in cutoff grade. The next time you see grade-tonnage data, don’t skip over it.  Take a minute to study it further to see what can be learned.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.   The entire blog post library can be found at https://kuchling.com/library/
Share

Mining Under Lakes – Part 2: Design Issues

This is Part 2 of a blog post related to open pit mining within bodies of water. Part 1 can be found at this link “Mining Under Lakes – Part 1“, which provides a few examples where this has been done successfully. Part 2  focuses on some of the social and technical issues the need to be considered when faced with the challenge of open pit mining within a water body.
dike construction in waterThe primary question to be answered is whether one can mine safely and economically without creating significant impacts on the environment.
The answer to this question will depend on the project location and the design of the water retaining structure.
I have worked on several projects where dike structures were built. I have also undertaken due diligence reviews of projects where dikes would be required. Most recently I have participated in some scoping level studies where mining within a lake or very close to a river were part of the plan.
In some instances, the entire orebody is located in the lakebed. In others, the orebody is mainly on land but extends out into the water. Each situation will be unique. In northern Canada, given the number of lakes present, it would be surprising if a new mining project isn’t close to a river or lake somewhere.

Dike concepts consider many factors

Different mining projects may use different styles of dikes, depending on their site conditions. Some dikes may incorporate sheet piling walls, slurry cutoff walls, low permeability fill cores, or soil grouting. There are multiple options available, and one must choose the one best suited for the site.
The following is list of some of the key factors and issues that should be examined.

ESG Issues

One’s primary focus should be on whether building a dike would be socially and environmentally acceptable. If it is not, then there is no point in undertaking detailed geotechnical site investigations and engineering design. One must have the “social license” to proceed down this path.
Water Body Importance: Is there a public use of the water body? It could be a fresh water source for consumption, used for agricultural or fishery purposes, or used as a navigable waterway, etc. Would the presence of the dike impact on any of these uses? Does the water body have any historical or traditional significance that would prevent mining within it?
Lake Turbidity: Dike construction will need to be done through the water column. Works such as dredging or dumping rock fill will create sediment plumes that can extend far beyond the dike. Is the area particularly sensitive to such turbidity disturbances, is there water current flow to carry away sediments?
At Diavik, a floating sediment curtain surrounding the dike construction area was largely able to contain the sediment plume in the lake.
Regional Flow Regime: Will the dike be affecting the regional surface water flow patterns? If the dike is blocking a lake outflow point, can the natural flow regime be maintained during both wet and dry periods?

Location Issues

If there are no ESG issues preventing the use of a dike, the next item to address is the ideal location for it.
Water depth: normally as the dike moves further away from land, both the water depth and dike length will increase. The water depth at the deepest points along the dike are a concern due to the hydraulic head differential created once the interior water pool is pumped out. The seepage barrier must be able to withstand that pressure differential, without leaking or eroding. A low height dike in shallow water may be able to use a simpler seepage cutoff system than a dike in deep water.
Islands: Are there any islands located along the dike path that can be used to shorten the construction length and reduce the fill volumes? Is there a dike alignment path that can follow shallower water zones?
Diavik open pit dikesPit wall setback: Given the size and depth of the open pit, how far must the dike be from the pit crest? Its nice to have 200 metre setback distance, but that may push the dike out into deeper water.
If the dike is too close to the pit, then pit slope failures or stress relaxation may result in fracture opening and increase the risk of seepage flows or catastrophic flooding. The pit wall rock mass quality will be the key determining factor in the setback distance.
Maximizing ore recovery: If the ore zone extends further out into the lake, maximizing ore recovery may require using a steep pit wall along the outer sections of the pit. This may require positioning haulroads with switchbacks along other sides of the pit rather than using a conventional spiral ramp layout.
At Diavik (see image), the A154 north open pit wall was pushed to about 60 metres of the dike to access as much of the A154N kimberlite ore as possible. Haulroads were kept to the south side of the pit.
It may be possible to recover even more ore by pushing out the dike even further. However, this may result in a larger and costlier dike or even require a different style of dike. There will be a tradeoff between how much additional ore is recovered versus the additional cost to achieve that. There will be a happy medium between what makes both technical sense and economic sense.

Design Issues

Once the approximate location of the dike has been identified, the next step is to examine the design of the dike itself. Most of the issues to be considered relate to the geotechnical site conditions.
Lakebed foundation sediments: What does the lakebed consist of with respect to soft sediments? Soft sediments can cause dike settlement and cracking, or mud-waving of fill material.
Will the soft sediments need to be dredged prior to construction, and if so, where do you dispose of this dredge slurry, and what impact will dredging have on the lake turbidity?
Lakebed foundation gravels: Are there any foundation gravel layers that can act as seepage conduits beneath the dike? If so, will these need to be sub-excavated, or grouted, or cut off with some type of barrier wall?  Sonic drilling, rather than core drilling, is a better way to identify the presence of open gravel beds.
Upper bedrock fracturing: Is the upper bedrock highly fractured, thereby creating leakage paths? If so, then rock grouting may be required all along the dike path to seal off these fractures.
Major faults: Are there any major faults or regional structures that could connect the open pit with the lake, acting as a source of large water inflow?. At Diavik, we attempted to characterize such structures with geotechnical drilling before construction. Upon review, I understand there was one such structure not identified, which did result in higher pit inflows until it was eventually grouted off.
Water level fluctuations: In a lake or river one may see seasonal water level fluctuations as well as storm event fluctuations. The height of the dike above the maximum water level (i.e. freeboard) must be considered when sizing the dike.
Ice scouring: In a lake or river that freezes over, ice loads can be an important consideration. During spring breakup as the ice melts, large sheets of ice can be pushed around and may scour or damage the crest of the dike. The dike must be robust enough to withstand these forces.
Construction materials available on site: Is there an abundance of competent rock for dike fill? Is there any low permeability glacial till or clay that can be used in dike construction? If these materials are available on site, the dike design may be able to incorporate them. If such materials are not available, then a alternate dike design may be more appropriate, albeit at a cost.

Conclusion

Each mine site is different, and that is what makes mining into water bodies a unique challenge. However many mine operators have done this successfully using various approaches to tackle the challenge.
Even at the exploration stage, while you are still core drilling the orebody through the ice, you can start to collect some of this information to help figure it all out.
The bottom line is that while mining into a water body is not a preferred situation, it doesn’t mean the project is dead in the water. It will add capital cost and environmental permitting complexity, but there are proven ways to address it.
On the opposite side, I have also seen situations where a dike solution was not feasible, so ultimately there are no guarantees that engineers can successfully address every situation. Lets hope your project isn’t one of them.
There could be a 3rd part to this post that discusses issues associated with underground mining beneath bodies of water; however that is not my area of expertise.  I would be more than happy to collaborate on a article with someone willing to share their knowledge and experience on that subject.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts. The entire blog post library can be found at https://kuchling.com/library/
Share

Mining Under Lakes – Part 1: Examples

Mining Under Lakes
Springpole Project

Springpole Project

I recently saw an investor presentation from First Mining Gold about their Springpole Project. The situation is that their open pit is located within a lake and will require the construction of a couple of small cofferdams to isolate the pit area from the lake. The concept is shown in this image.
Over the last couple of years I have been involved in a few early-stage studies for mining projects in which nearby bodies of water play a role in the design.    In Canada’s north there are thousands of lakes and rivers, so its not surprising to find mines next to them.
That got me thinking about how many other mines are in the same situation, i.e. projects that may be located very close to, or within, a lake, river, or ocean. Hence I have compiled a short list of a few such mines.
I have been directly involved with some of those in the list, while others are only known to me with limited detail. Some mines I had never heard of before, but their names were provided to me by some Twitter colleagues.
My observation is that building a mine within, or adjacent to, a body of water is nothing new and this has been done multiple times successfully.
Some of these projects may refer to the dams as “dikes”, “cofferdams”, “sea walls” but I assume they are all providing roughly the same function of holding back water for the life of the project.  They are not viewed as permanent dams.
This is Part 1 of a two-part blog post. Part 1 provides some examples of projects where water bodies were involved in the design. Part 2 provides a discussion on specific geotechnical and hydrogeological issues that would normally have to be examined with such projects.

Some Lake Mining Examples

The following are some examples of operating mines involving lakes. I have captured a few Google Earth images, unfortunately some have only low resolution vintage satellite imagery.

Diavik Diamond Mines, NWT

This is a project I was working on with in 1997 to 2000 while it was still at the design and permitting stage.  My role focused on pit hydrogeology and geotechnical as well as mine planning.
The project would require the construction of three dikes in sequence to mine four lakebed kimberlite pipes.
The three dikes were named after the associated kimberlite pipe being mined inside it; A154, A418, and A21.
The first dikes were built in 2002 and the last dike (A21) was completed in 2018.
The total dike length for the three dikes is about 6.2 km.
For those interested in learning a bit more about Diavik, I have posted an earlier article about the open pit hydrogeology there, linked to at " Hydrogeology At Diavik – Its Complicated".
Diavik mines

Gahcho Kue, NWT

This is a DeBeers diamond project was built in 2016 and required the construction of several small dikes to allow access for open pit mining.    The photos show the pre-mining situation and the site as it is today.   One can see the role the lake would play in the site layout and the need for multiple small dikes.
Gahcho Kue diamond mine

Meadowbank, NWT

This is an Agnico-Eagle gold mining operation built in 2010 that required a cofferdam to be built around one of their open pits (see image).
The total dike length is about 2000 metres.   I don't know much more about it than that unfortunately.
Meadowbank Mine

Cowal Gold Mine, Australia

Yes, a lake in Australia ! This is a former Barrick operation, now owned by Evolution Mining, and is another example where the mine is located within the shoreline of a lake (Lake Cowal).    I don't know much about this, the name was kindly provided to me by a colleague.
The total dike length appears to be about 3000 metres.
Cowal Gold Mine

Rabbit Lake Sask

The historical Rabbit Lake uranium mining operation required the construction of cofferdams around a few of their open pits.  They are now reclaimed and flooded.
Rabbit Lake uranium

St Ives Gold Mine, Australia

This is a unique situation in that several pits are located within an ephemeral (intermittent) salt lake and dikes were required to prevent pit flooding during wet season.
St Ives gold mine

Some River Mining Examples

The following are some examples of operating mines involving rivers.  Rivers provide a somewhat different design challenge since they have flowing water, who's volume and velocity may change seasonally.    Constrictions in the river created by the dike itself may increase the flow velocity and erosion potential.

Gorevsky Mine, Siberia

This lead-zinc operation has an orebody that extends into the Angara River.
This mine has built a fairly large cofferdam into the river, and is currently mining a large pit within it.  The total cofferdam length appears to be about 4000 metres.
It would be interesting to see how close the pit will get to the cofferdam.   We'll check back in a few years.
Gorevsky Mine

BHP Suriname Bauxite Mine

This is a project I was involved with several years ago.  The bauxite deposit extends beneath the Suriname River and the goal was to mine as much ore as possible.
Given the flow rates in the river, especially during the wet season, it would be difficult to maintain a cofferdam out into the river.
The shoreline overburden consisted of sands and soft clays, so the decision as made to construct a sheet piling wall along the river bank to protect the pit from river erosion.   This was mined out successfully and eventually reclaimed.
Suriname Bauxite Mine

McArthur River, Australia

In situations where the river (creek) is small enough and the topography allows, one can divert the entire river around the mine.
There are several examples of this in Canada and elsewhere.  Here’s the McArthur River lead-zinc mine in Australia, where they channeled their small river around the open pit.
McArthur river diversion

An Ocean Example

There are some examples of mining near the ocean. These operations may need to deal with large storm water level surges and large tidal fluctuations.   The Island Copper Mine on northern Vancouver Island is an example where they mined close to the shoreline but not actually into the ocean (as far as I am aware).

Cockatoo Island Mine, Australia

This interesting iron ore mine has an ore zone that dips 60 degrees, is 35 metres wide, with a strike length of more than one kilometre.
A sea wall was constructed to prevent any tidal water from entering the open pit that was to be mined, with reportedly high tidal fluctuations there.
Cockatoo iron mine

Conclusion

As one can see, the idea of mining into a body of water is nothing new.   Its not a preferred situation, but it can be done economically and safely.   The technical challenges are straightforward, and engineers have dealt with them before.  However there also are instances where the design could not economically address the water issue, and thus played a role in the mine not getting built.
If you know of other mines not listed above that have successfully dealt with a water body, please let me know and I can update this blog post.
This concludes Part 1.  Part 2 can be read at this link " Mining Under Lakes – Part 2: Design Issues" discusses some of the concerns that engineers need to consider when building a mine in these situations.

Pantai Remis tin mine

Finally, the worst-case scenario is shown in this grainy video of a tin mine (Pantai Remis Mine) pit slope failure.  It seems they mined too close to the ocean.  Watch to the end, its hard to believe. Its looks like something out of a Hollywood disaster movie.

 

Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.   The entire blog post library can be found at https://kuchling.com/library/
Share

Steeper Pit Slopes Can Save Money

We likely have all heard the statement that increasing pit wall angles will result in significant cost savings to the mining operation.
What is the potential cost saving?
The steeper wall angles reduce waste stripping volumes, which also provide other less obvious benefits.
I was recently in a situation where we undertook some comparative open pit designs using both 45 and 50 degree inter-ramp angles (“IRA”). I would like to share some of those results and discuss where all the benefits may lay.

Comparative Pit Designs

In this project, four separate open pits were designed with 45 and 50 degree IRA’s in an area with hilly topography. Some of the pits had high walls that extended up the valley hillsides. Its not hard to envision that waste stripping reductions would be seen along those areas with steepened walls.
The results of applying the increased  inter-ramp angle to each of the four pits is shown in the Bar Chart. Note that the waste reduction is not necessarily the same for each pit.  It depends on the specific topography around each pit.
However, on average, there was an overall 15% reduction in waste tonnage.
The Table shown below presents the cumulative tonnage for all four pits. The 50 degree wall results in a waste decrease of 25.4 million tonnes (15%), with a strip ratio reduction from 5.8:1 to 5.0:1.
There is also a very minor decrease in ore tonnage. This is because the 50 degree slopes did lose some ore behind the walls that is being recovered by the 45 degree slope.
In both scenarios the project life would be about 10 years at an assumed ore processing rate of 3 Mtpa.

4 Positive Impacts of Steeper Walls

In general one can typically see four positive outcomes from adopting steeper pit walls. They are as follows:
1. Cost Savings: The waste tonnage reduction over the 10 year life would be about 25.4 million tonnes. At a mining cost of $2.00/tonne, this equates to $50.8 million tonnes spent less on stripping. This could move the project NPV from marginal to profitable, since most waste is normally stripped towards the front part of the mining schedule with less discounting.
The next time you are looking at the NPV from an open pit project, take a quick look to see if the pit slope assumptions are conservative or optimistic. That decision can play a significant role in the final NPV.
2. Equipment Fleet Size: Over the 10 year life, the average annual mining rate would range from 20.5 Mtpa (45 deg) to 18.1 Mtpa (50 deg). On a daily basis, the average would range from 56,100 tpd (45 deg) versus 49,700 tpd (50 deg). While this mining rate reduction is not likely sufficient to eliminate a loader, it could result in the elimination of a truck or two.   This would have some capital cost saving.
3. Waste Dump Size: The 15% reduction in the waste tonnage means external waste dumps could be 15% smaller. This may not have a huge impact but could be of interest if waste storage sites are limited on the property. It could have a more significant impact if local closure regulations require open pit backfilling.
4. Pit Crest Location: The steeper wall angles result in a shift in the final pit crest location. The Image shows the impact that the 5 degree steepening had on the crest location for one of the pits in this scenario.
Although in this project the crest location wasn’t critical, there are situations where rivers, lakes, roads, mine facilities, or public infrastructure are close to the pit.  A steeper wall could improve ore recovery at depth while maintaining the same buffer setback distance.

Conclusion

Steeper pit walls can have multiple benefits at an open pit mining operation. However, these benefits can all be negated if the rock mass cannot tolerate those steeper walls. Pit wall failures could be minor or they could have major impacts. There are the obvious worker safety issues, as well as equipment damage and production curtailment concerns with slope failures.  Public perception of the mining operation also comes into play with dangerously unstable slopes.
Steepening of the pit walls is great in theory, but always ensure that geotechnical engineers have confirmed it is reasonable.
It is relatively easy to justify spending additional time and money on proper geotechnical investigations and geotechnical monitoring given the potential slope steepening benefits.
When designing pits, there is some value in looking at alternate designs with varying slope angles to help the team understand if there are potential gains and how large they might be.
In closing, I previously wrote a related blog post about how pit walls are configured to ensure safe catch bench widths and decisions as to whether one should use single, double, or triple benching. That earlier post can be read at this link. Pit Wall Angles and Bench Widths – How Do They Relate?
Feel free to share your personal experiences if you are aware of other benefits (or even downsides) to steeper pit walls that I did not mention.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share

Games People Play

Are you a board game player?  Personally I am not.  However I understand there is a huge board game community out there. These game enthusiasts meet in small coffee shops and attend large gaming conventions. I read that 35% of Americans say they play board games several times a month. Think about how many board games you may have laying around in your own place, even if you’re not a hard core gamer.
Recently an avid board game player sent me an email asking if I was aware that there several mining related games. That was a surprise to me. Who would create a board game about mining and for what demographic market?
Curiosity took over and I had to check out the links sent to me on the Board Game Geek website. Here’s a few of the games and what they do.   Now that Germany may be moving back into coal, the first three games may come back into fashion.  The 4th game listed is a bit of a head scratcher.

A few of the mining board games

Game 1: Haspelknecht: The Story of Early Coal Mining (2015)
This game is part of a coal-mining game trilogy created by Thomas Spitzer in Germany. The players take the role of farmers with opportunities to exploit the presence of coal in the Ruhr region of Germany. During the game, players acquire knowledge about coal, extend their farms, and dig deeper in the ground to extract more coal.
Players must select the correct tasks while being mindful of quickly accumulating pit water, for it can stall efforts and prevent extraction of coal.  The game info link is here.
Game 2: The Ruhr: A Story of Coal Trade (2017)
In the second game of Spitzer’s trilogy, you are still in the Ruhr region in the 18th century, at the beginning of the industrial revolution. The Ruhr river presented a transportation route from the coal mines. However, the Ruhr was filled with obstacles and large dams, making it incredibly difficult to navigate.
The players transport and sell coal to cities and factories along the Ruhr river in the 18th and 19th centuries. In the beginning, players have access only to low value coal but can gain access to high value coal. The players also build warehouses, locks, and export coal to neighboring countries in the pursuit of the most points.
The info link is here.
Game 3: Schichtwechsel: Die Förderung liegt in deiner Hand (2021)
This game may still be in German text only. Players are the administrator of a coal mine, and experience competition while living through a piece of Ruhr Valley history.
They bring coal and overburden from underground to the surface, let the miner go through a “shift at the colliery”, produce coke, or build the typical colliery settlements.
The info link is  here.
Game 4: The Cost (2020)
This game takes on a more negative view of the mining industry. It is described as “A bold take on the economics in the brutal industry that is asbestos.” The game players assume the role of a global asbestos company.
Players make their fortune in mining, refining, and shipping. Whoever ends the game with the most money wins. The last part of the description is the gem “When players mine or refine asbestos, they must choose to either maximize profits for short-term gains or sacrifice their hard-won money to minimize deaths, thus sustaining the industry.” That’s every mining executive’s dilemma; profits or deaths.   The info link is here.
Some of these game boards look more complicated than the actual industry. To find other games you can go to the Board Game Geek website and search for different themes. Most mining games listed there are not realistic but are more about dwarves mining gems or they just have an activity called “mining”.   Here’s one called Copper Country.

Free Excel Mining Game

In 1983 my brother, at the age of 10, got his Commodore 64 computer and was eagerly learning to program in BASIC. He was always looking for ideas on what he could write programs about. I had graduated from McGill in Mining Engineering a few years earlier, so I suggested he write a simple computer game about mining as his project.
I provided him with the logic and in no time he had it written and functioning. That game is long gone, likely at the bottom of a landfill stored inside the chips of his Commodore 64. Some 40 years later, my brother is still coding as a software development manager. I guess I managed to convince him the mining industry wasn’t a career path.
Over the last few months I decided to learn VBA (Visual Basic for Applications). VBA is a programming language the works with Microsoft Office products, mainly Excel.
I always enjoyed programming. In university we wrote FORTRAN programs using stacks of punch cards to feed the machine the code. I had also learned the BASIC language, from my brother’s VIC 20 and Commodore computers.
A good way to learn something is to watch a few pf the many tutorial videos on YouTube. An even better way to learn VBA is by taking on an actual coding project from scratch. So, what worked 40 years ago, would work again. Rather than write something useful, I decided to re-write the mining game from 1983, albeit enhanced with the Excel application capability and more years of personal mining experience.
This coding process would force me to learn how to write code, figure out logic, create loops, if-then statements, and handle debugging. Already knowing Excel makes the entire process easier.  Combining Excel functionality with VBA delivers capabilities that would have been difficult to do in BASIC alone.  Note: It appears that BASIC is no longer in use, having been replaced by Python as the preferred programming language.

Download it.. if curious

If you are curious about the capability of VBA, the Excel mining game can be downloaded. A descriptive overview of the game is included in the PDF file at this link.

Junior Mining CEO game screenshot

The very simple game is called Junior Mining CEO. The object is to find gold, raise the share price, and not go bankrupt given the pitfalls that often befall the mining industry. The input parameters have a lot of optionality, although I have protected the macro code itself for this edition. You can borrow money and issue equity to fund your mining activity.
The Excel file can be downloaded at this link. The was written using Excel 365 but it may also work on older versions of Excel.
You will first need to save the game to your computer to run the macros. Since there are macros, many computers will disable such Excel files because they can contain viruses. You may need to toggle the file Properties in File Explorer to unblock the file to allow the macros to run.
Is there a junior mining corporate sponsorship opportunity here? Sure. For a small fee, I will add your company logo to the game and pre-set all the input parameters so that everyone is a big winner all the time.

Conclusion

As mentioned in a blog from a few months ago, “ A Junior EIT Mining Story” some gamification of mining may help introduce and educated people on the industry. Augmented reality (AR) and Virtual reality (VR) are both technologies that can be used to help reach out to the younger generations (I’m not talking about investor outreach).
How about a new board game that does to mining what Monopoly did to real estate investing? Look at real estate prices today, no doubt being influenced by everything we learnt playing Monopoly as kids.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share

Clays and Mining – Friends or Foes?

Overburden is a generalized termed used to describe unconsolidated material encountered at a mine.  It can consist of gravels, sands, silts, and clays and combinations of each. Usually overburden is not given much focus in many mining studies. Very often, the overburden as a unit, is not adequately characterized.
This blog will explain why proper characterization can be an important issue,  particularly the clay component.
I also want to share some personal mining experiences with clays, all types of clays.  There is more to them than meets the eye; a fact often not apparent to those involved only in hard rock mining.
Clays have unique geotechnical properties that can make for challenging situations and require special consideration in project design.   Many simply view clay as a sticky cohesive material – no big deal. So let’s examine this a bit further. I tried to avoid geotechnical lingo where possible, since this blog isn’t being written for geotechnical engineers.
There are several types of clays, or clay-like materials that can be encountered in mining. Here are the ones that I have been lucky (or unlucky) enough to have dealt with over the years.
  • Normally consolidated clays
  • Over-consolidated clays
  • Sensitive (or quick) clays
  • Swelling clays
  • Saprolite clays
  • Kimberlite clays (muds)

What are the challenges?

Each of the clays listed above can be found in different locations, have unique properties, will behave differently, and can create specific mining challenges.   Clays can also cause problems in process plant circuits, but that is a subject outside my area of expertise.

Normally consolidated clays

These are the clays most people are familiar with, i.e. a sedimentary deposit of very fine particles that have settled in a calm body of water.   Normally consolidated clays are generally not a problem, other than having a high moisture content.  As such, they can be very sticky in loader buckets, truck boxes, and when feeding crushers.
When wet, they can become sloppy and difficult to handle efficiently.  They can creep and run when placed into waste dumps.  For these reasons, engineers must be aware if a large proportion of the overburden will consist of clays so they can avoid surprises.

Over-consolidated clays

These clays have undergone greater vertical compression in their history than in their current condition.  For example, perhaps they were once pre-loaded and compressed by a mile of glacial ice sheet during an ice age, which has subsequently melted.
Clays in general consist of very fine plate like particles, as shown in this sketch.   In over-consolidated clays, these particles have been flattened and tightly compressed as in the right image.   The result is that the clay may be dense, have a good cross bedding shear strength, but very low shear strength along the plates.  This characteristic is analogous to the lubricating properties of graphite, which is facilitated by sliding along graphite plates.
My experience in working with over-consolidated clays was at the Fort McMurray oil sands mining operations.  In that region the Clearwater clays formed part of the overburden sequence above the oil sands.  Stripping these clays with trucks and shovels was not exceptionally challenging.  They had low moisture content and were stiff.   The challenge really came when needing to build on top of them, for example building a waste dump or tailings dam.
The cross-bedding shear strength was good, with peak friction angles exceeding 25 degrees.  However after any creep or deformation, the peak shear strength was gone and the residual friction angle would now control stability.   The residual friction angles could drop as low as 6 degrees (very weak) and, upon surcharging the clay could maintain high internal pore pressures.   Due to these factors it was not uncommon to see tailings dams or waste dumps with 15:1 (H:V) downstream slopes.  This compares to the 3:1 slopes one may normally see at hard rock mine sites.
Building a 15:1 dam or dump is much less volume efficient than building a 3:1 embankment.  It also doesn’t take much instability to cause an embankment to creep along a foundation with only a 6-degree friction angle.  Hence the over-consolidated clays presented a unique engineering challenge when working in the oil sands.

Sensitive (quick) clays

Referring to the clay particle sketch shown above, quick clays represent a card house structure (on the left image).  These clays were often deposited in a quiet marine environment, where electrical charges prevented the clays from settling uniformly.  Instead, the clay particles tend to stack up like a house of cards.  The large void spaces are filled with water, whereby moisture contents can exceed 100% by weight.
When these clays are disturbed by vibration or movement, the house of cards structure collapses.  Combined with the excess void water, these clays will flow…. and flow a lot.   This video shows a slope failure in quick clays in Norway.  Try to stop that failure once it has initiated.
My experience with sensitive clays was at the former BHP bauxite mining operations along the northern coast of Suriname.   There were Demerara clay channels up to 20m thick over top of many of their open pits.   The bucketwheel excavators used for waste stripping would trigger the quick clay slope failures, sometimes resulting in the crawler tracks being buried and unfortunately also causing some worker fatalities.
I recall walking up towards a bucketwheel digging face as the machine quietly churned away.   About 70 metres from the machine, we would see cracks quietly opening all around us as the ground mass was starting to initiate its flow towards the machine.   Most times the bucketwheel could just sit there and dig.  Instead of the machine having to advance toward the face, the face would advance towards the machine.
To address the safety issue, eventually mine-wide grids of cone penetration tests were used to define the Demerara clay channels.  Dredges were then brought in to remove these channels before allowing the bucketwheels to strip the remaining sands and normally consolidated clays.

Swelling clays

In some locations, mines may contain swelling clays.  The issue with these clays is that they can absorb water rapidly, swell by 30%, and become extremely soft to operate on.  If they form part of the ore zone and find their way to the tailings pond, one may find they don’t want to settle out in the pond. Water clarification and clean water recycle to the plant can become an operational issue.   Mineralogy tests will indicate if one has swelling clays (smectites, montmorillonites, bentonite).  The swelling clays do have a functional use however, discussed later.

Kimberlite clays (muds)

The formation of the diamond deposits in northern Canada often involved the explosive eruption of kimberlite pipes under bodies of water. The lakebed muds and expelled kimberlite by the eruption would collapse back into the crater, resulting in a mix of mud and kimberlite (yellow zones in the image).   This muddy kimberlite could be soft, weak, and difficult to mine with underground methods.
Normally as one descends deeper into the kimberlite pipe,  the harder primary kimberlite dominates over the muddy material.   An upside is that the muddy kimberlite can be scrubbed fairly easily during processing, with the very fine clay particles being washed away.

Clays can’t be all bad?

Encountering clays at a mine site can’t be always negative?  There must be some benefits that clays can provide?   Well there are a few positive aspects.

Saprolite clays 

At many tropical mining operations (west African gold projects for example) the upper bedrock has undergone weathering, resulting in the fresh rock being decomposed into saprolite.  This clay-rich material can exceed 50 metres in thickness, can be fairly soft and diggable without blasting.   This is an obvious mining cost benefit.
As well, grinding circuits can easily deal with saprolite.  For example, if a 1000 tpd grind circuit is designed for the underlying deeper bedrock, it may be able to push through 1400 tpd of saprolite.   This would yield a 40% increase in mill throughput for little added cost.  This will boost early gold production.  However as the blend of saprolite to fresh rock declines over the years as the pit deepens, the plant throughput will decrease to the original design capacity.
One concern with saprolite sometimes is its sticky nature.   A truck load of saprolite ore dumped on a crusher grizzly may just sit there.  Possible some prodding or water flushing may be required to get it moving.  Nevertheless, this is normally an easily resolvable operating issue.

Clay core dams

One of the ways miners build water retention or tailings dams is to use mined waste rock.   The issue with this is that a dam built solely with waste rock will leak like a sieve, which can lead to piping failure.  One solution is to build an internal clay core in the center the dam to act as a seepage barrier.   Having on-site access to good quality clean clay fill is a benefit when such dams are required.   If the clay fill isn’t available at site, then more complex synthetic liners or internal seepage control measure must be instituted.
Compacted clay fill can also be used as a pond liner material for water retention ponds.
One can also purchase rolls of geosynthetic clay liners (GCL), whereby a thin layer of dried swelling clay is encapsulated between two sheets of geotextile.  Once the liner is laid out and re-hydrated with water, the clays swell and will act as an impervious liner.   The installation approach is somewhat simpler than for HDPE liners and such liners can be self-healing if punctured.  A downside is that the transport weight of these GCL liners can be significant.
See, there are some positives with having clay at site.

Conclusion

All clays are not the same.  The mining of clays can create unique challenges for mining engineers and operating personnel.   Whenever I see study happily mention that their open pit mine waste consists of “free digging overburden”, I say to myself “Be careful what you wish for”.
One must ensure that the overburden is properly characterized, even though it may be viewed as an unimportant or uninteresting material.  Determine whether it consists of gravels, sands, silts, tills, or clays, or combinations thereof.   It can make a big difference in how it is mined, disposed of, and whether it can have any secondary uses on site.  In many studies that I have reviewed, the overburden tends to be forgotten and does not get the technical respect it deserves.
Please feel free to share any thoughts on your experience in working with clays.
We had to build mine haul roads across large swamps underlain by soft clays.   One option was to use geo-textiles or swamp vegetation to assist us.  Another option was to place the sand fill hydraulically.  You can read how we did this at the following blog post “Using Pumped Sand to Build Mine Roads“.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted.   Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share

A Junior EIT Mining Story

We know the mining industry is having trouble attracting talent in all sorts of disciplines, including operations, technical, and supervision. Industry people have no shortage of ideas (right or wrong) on how this issue can be addressed in the future. Myself…I don’t really have any good suggestions.
Not long ago I was speaking with a 2020 graduate mining engineer (EIT = Engineer in Training). During our conversation, I was curious to know what attracted him to the industry and if he had any advice on how to reach out to others in his age group. I asked if he was willing to share his thoughts on my blog site. After all, who better to hear from than a recent graduate. He said “yes”, so for your interest, here is his story and his thoughts. (I decided to leave his name out of this article although he was not insisting on anonymity.)

So here’s the story (in his words)

Mining has been a part of my life for as long as I can remember. Being born in Sudbury, many of my family members have been, or are currently involved, in mining through a variety of occupations, including my father who I idolized. However, I never knew my true interest in the industry until my 11th-grade technology class. I had a teacher who was passionate about the mining industry, and he created a project that involved developing a very basic mine design.
Once I started the project, I realized that I enjoyed the design work, as it requires problem-solving which constantly stimulates the mind. After the conclusion of this project, I started doing my own research to expand my knowledge and realized that the financial side of mining had great interest to me as well. This led me at age 16 to start investing in the mining sector, which I continue to this day.
With this developed interest, and my family’s mining history, the decision to study Mining Engineering at Laurentian University was an easy decision. It allowed me to support my hometown and will allow me, given my career ambitions, to put this small school on the international map.
Before my first year of university, I had a summer job tramming at Macassa Mine in Kirkland Lake Ontario, which has been in production since 1933. My mentality was to get the boots on the ground and get the job done, whatever it took (with proper safety precautions of course). Using rail systems, dumping ore cars manually, jackleg drilling, etc. gave me the perspective that mining was archaic, mining was rough, and mining was only about the ounces.
Therefore, when I started the Mining Engineering program at Laurentian University in 2016, I already had a (somewhat negative) preconceived notion of the mining industry, but as my short career progressed, my opinions morphed into something different, something more positive.
Now that I have graduated and been employed for a couple of years, my perspective has changed. However, I feel that the perspective of the general population has not. People within mining have a (positive) bias and realize its importance in our everyday lives. This is showcased in the famous saying “if it is not grown, it is mined” and I believe that to get the industry to progress at an even faster rate, we need to get everyone on board.
It cannot be an industry that just takes from the Earth, it needs to be seen as one that values sustainability, supplies the world with required goods, and creates jobs with high employee satisfaction. Although this has started with companies taking more of an interest in stakeholder value and employee job satisfaction, based on my limited years in the industry, there is still lots of room for growth.
To change the negative view around mining, I believe the main focal point should be electric equipment and the ability for remote operation/work. With all this newly developed technology at our fingertips, I know that future operations will be safer and more sustainable, which should be better portrayed.
The battery-electric equipment will surely increase employee satisfaction since I know firsthand that one of the worst feelings as a worker is to have a scoop operating in a heading that is already 25+ degrees. It will also create more sustainability since the industry can transition from being reliant almost solely on fossil fuels.
In addition, I believe that remote equipment operation is not being used to its full capacity or explained to the younger generation. Right now, there has been equipment running in Canada that was operated in Australia. What is stopping mines from having equipment operators all over the world in urban office spaces or out of their own homes? I believe that for a company to visit a high school, or even a trades school, to sell the idea that you can operate a massive piece of equipment from the creature comforts of home, almost like a real-life video game, would be quite compelling to this audience.
Even creating a mining simulation video game where you can run through a story of being a manager, excavator/scoop operator, truck driver, etc. would get the thought of mining brought into the coming generations at a younger age. This would increase the talent pool from the more typical operator because more and more youth are getting skilled at remote operation through video games due to their increased screen time.
Not only equipment operators, but technical staff could be made fully, or partially, remote. When I describe my job to my (non-mining) peers, many are interested since mining is a fast-paced, stimulating, and rewarding industry.
But as soon as I describe the remote nature of the work, many young professionals, or high school students, get turned away. Therefore, showing teenagers, through school presentations or workshops, that a technical career in mining can lead you down so many avenues (scheduling, ventilation design, drill & blast, etc.) would pique their interest, but I believe adding the ability to work remote, with some occasional travel, would drive the point home.
InternPeople get comfortable and people are afraid to leave home, so selling a career that allows for boundless flexibility in job tasks and constant stimulation while living wherever you desire could allow a shrinkage in the current technical gap.
Overall, the mining awareness and outreach (approach) is still old school. Getting to youth and teenagers through various media streams could be the key to getting engagement from not only the current mining towns but larger urban centres as well.
I mentioned a mining simulation video game previously, but what is stopping us there. Many of my peers, and youth younger than myself, are entering the professions of doctors, lawyers, finance, or criminal investigators.
I might be wrong, but, intriguingly, these are industries are the base professions glorified on TV. Why not develop more TV shows based on mining? I know that there would be some population interest considering many people ask me if the gold we mine underground looks like what comes out of the pans in Yukon Gold Rush.
So do I think the mining industry is archaic…. not anymore.
Do I think the mining industry is rough… somewhat.
Do I think it is only about the ounces…., yes, since a mine will not run any other way.
However, I believe that there has been more importance placed on employee and stakeholder satisfaction. So, with more time, and more engagement from the public of all ages, I think this industry can have a bright future ahead.
END

Conclusion

Firstly, I would like to thank this engineer for taking time to write out his well formed thoughts, and for allowing me to share them.
Many of the mining people I meet are following along in family footsteps. No surprise there. However, the industry cannot rely on that farm system alone. It should be reaching out to broader society, although that may require some out-of-the-box thinking. People’s attitudes and personalities are different today than they were 20 years ago.  Many different doors are being held open as career options.
The discussion above has some interesting ideas from a person who would be the target of outreach efforts. It likely will take more effort than simply telling people “Hey, your iPhone uses metal, therefore mining is good, and you should work in mining”.
This guest blog post is an industry perspective from the view of a young engineer.  If you interested in the perspective from a seasoned engineer who has worked around the globe, check out the book that is described in this blog post “Life as an Engineer – Read All About It“.
Note: You can sign up for the KJK mailing list to get notified when new blogs are posted. Follow me on Twitter at @KJKLtd for updates and other mining posts.
Share